Design basis for gypsum mineral powder plant
The design basis starts with the rock, not the machine. Gypsum is rated at 20–60 MPa compressive strength with very low abrasiveness, low–medium moisture sensitivity and a loose bulk density around 1.25 t/m³. Soft and prone to caking; drying and air-flow control in the grinding circuit matter more than crushing force. A change in one stage changes the circulating load in all the others.
A mineral powder plant must reach a specified D97 with stable specific surface, constrained by classifier sensitivity and dust-collector capacity. The commercial priority is fineness distribution. For this combination HAMAC works from an indicative design point of 25 t/h of saleable product, with a maximum feed top size near 400 mm and target fractions of ground powder, 0–10 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gypsum · 20–60 MPa · abrasion very low |
| Design throughput | 25 t/h saleable product (5–30 t/h scenario band) |
| Maximum feed size | ~400 mm |
| Target product | ground powder, 0–10 mm |
| Loose bulk density | 1.25 t/m³ |
| Suggested circuit | impact / hammer → screen → grinding mill |

Why start-up instability appears in this circuit
The plant cannot hold a steady feed during its first weeks. In a gypsum mineral powder plant this is usually a system symptom rather than a single machine fault. Most of these problems are diagnosed at the screen, not at the crusher.
- interlocks and feeder ramp rates were never tuned together
- settings were changed without a commissioning log
- operators were trained on a different circuit
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For gypsum at 25 t/h the working train is impact / hammer → screen → grinding mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gypsum and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~31 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.25 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 80 kW order-of-magnitude connected load |
The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 40% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Verify every interlock in no-load and loaded runs
- Sign off the settings log with both parties
- Repeat a full sieve analysis after the first 100 hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 25 t/h nominal |
| Grading | Full sieve analysis, agreed standard, ground powder, 0–10 mm |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 80 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gypsum, while fineness distribution determines how much lost production actually costs. Most of these problems are diagnosed at the screen, not at the crusher.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 25 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.