Overview
A iron ore crushing plant turns raw iron ore into graded aggregate, ore feed or industrial mineral. Material properties — Mohs 5.5, compressive strength ~160 MPa, medium abrasion — decide the circuit.

Iron ore material profile
| Property | Value |
|---|---|
| Mohs hardness | 5.5 |
| Compressive strength | 160 MPa |
| Abrasion | Medium |
| Recommended circuit | jaw + cone (+ HPGR option) |
Recommended circuit
HAMAC configures Iron ore plants as: jaw + cone (+ HPGR option). High tonnage; often processed before beneficiation.
Typical equipment
- PE Series Jaw Crusher — Jaw crushers are often used for primary crushing in mine material crushing.
- HPT Multi-Cylinder Hydraulic Cone Crusher — Hydraulic multi-cylinder cone crusher for secondary and tertiary crushing of limestone thr
- Symons Cone Crusher — S series Symons cone crusher is a kind of high efficiency cone crusher, which integrate op
Capacity range
From 30 t/h contractor units to 1,000+ t/h quarry lines, with multi-deck screening for several saleable fractions.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Iron ore |
| Mohs hardness | 5.5 |
| Compressive strength | ~160 MPa |
| Abrasiveness | Medium |
| Recommended circuit | jaw + cone (+ HPGR option) |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | three-year view |
Ask for the same table from any competing supplier; without it, an offer for iron ore crushing cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | three-year view |
| Site condition | a greenfield site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for iron ore crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Confirm the haul-road and stockpile plan with a greenfield site in mind before fixing conveyor lengths.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
A HAMAC project manager stays with the order from the first data sheet through hand-over in your market.

What to verify before you sign
- Dust and noise control designed to the local emission limits for your market.
- Control system language, telemetry and remote diagnostics availability.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Guaranteed power draw and the maximum mechanical availability trade-off it implies.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 18% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a greenfield site.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
For manufactured-sand production, protect the maximum mechanical availability requirement explicitly in the contract documents.
Commissioning checklist
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check lubrication levels, grease lines and oil cooler operation.
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure noise and dust at the operator position against the local limit.
- Record power draw, tonnage and chamber pressure at steady state.
- Record the baseline grading curve for each product fraction.
- Verify rotation direction on every motor before coupling.
Keep the signed record; it is the only defensible baseline for later performance disputes.