Overview
Wear parts are the largest variable cost on a HCS Hydraulic Cone Crusher. HAMAC supplies matched consumables and a recommended stock list with every plant.

Main consumables
- Chamber liners / blow bars / Impact plates.
- Rotors, distributor plates and anvils (VSI).
- Screen meshes for every deck.
- Belts, bearings, seals and sensors.
Liner material grade
Mn13 / Mn18 / Mn22 work-harden under impact; high-chrome resists abrasion in low-impact duties. Choice follows the rock, not the price.
Recommended stock
- One full set of chamber liners or blow bars.
- Screen meshes for every deck.
- Belts, bearings and seals.
- Electrical consumables and sensors.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | HCS Hydraulic Cone Crusher |
| Category | Cone Crusher |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | five-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published HCS Hydraulic Cone Crusher model data
| Model | Cavity | Feed opening | Min opening | Capacity | Maximum Power |
|---|---|---|---|---|---|
| HST100 | S1(EC) | 240 mm | 22 mm | 85-170 t/h | 90 kW |
| S2(MC) | 200 mm | 19 mm | 70-130 t/h | ||
| H1(F) | 135 mm | 10 mm | 45-115 t/h | ||
| H2(MF) | 65 mm | 8 mm | 35-80 t/h | ||
| H3(UF) | 35 mm | 4 mm | 27-60 t/h | ||
| HST160 | S1(EC) | 360 mm | 25 mm | 120-345 t/h | 160 kW |
| S2(MC) | 300 mm | 22 mm | 105-305 t/h | ||
| S3(C) | 235 mm | 19 mm | 90-275 t/h |
HST single cylinder hydraulic cone crusher integrates mechanical, hydraulic, electrical, automation, intelligent control and other technologies, and can be widely used in medium, fine and. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | five-year view |
| Site condition | a remote mine site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for hcs hydraulic cone crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Review the crusher chamber profile with the liner supplier against the feed material.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Written performance guarantee, sampling method and acceptance-test protocol.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
- Control system language, telemetry and remote diagnostics availability.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Energy draw in kW and the expected kWh per tonne at the design duty.
Share this list with a full-time plant team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On contract crushing on short-term sites, the lowest energy per tonne objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Using one liner profile for both secondary and tertiary stages.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Buying lowest energy per tonne on price alone and losing it in availability.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming the manufacturer's warranty covers wear parts and consumables.
For contract crushing on short-term sites, protect the lowest energy per tonne requirement explicitly in the contract documents.
Commissioning checklist
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Check belt tracking, chute build-up and transfer-point dust.
- Confirm the direction and tension of every belt under no load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify rotation direction on every motor before coupling.
- Record power draw, tonnage and chamber pressure at steady state.
- Confirm all guards, emergency stops and pull-wire switches function.
- Dry-run the plant empty for the specified period and record vibration.
Keep the signed record; it is the only defensible baseline for later performance disputes.