Overview
Choosing a Tracked Jaw Crusher Plant starts with the rock and the target product, not a catalogue number. The steps below turn your project data into a defensible model choice.

1. Start with the material
- Hard, abrasive rock (granite, basalt, quartz): compression crushing, premium Mn liners.
- Soft rock (limestone, marble, dolomite): impact crushing for shape at lower cost.
- High silica (river pebble, quartz): plan VSI + wear budget.
2. Size to saleable t/h
Add 10–20% surge to nameplate capacity; undersizing is a permanent bottleneck, oversizing wastes capital.
3. Match the product grading
Product size and shape (flakiness index) decide chamber and screen deck setup.
Pre-order checklist
- Feed size and max lump.
- Required t/h and product fractions.
- Site power (voltage / frequency) and mobility need.
- Local standards (CE, GOST, etc.).
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Tracked Jaw Crusher Plant |
| Category | Tracked Crushing Plants |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | single-project view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published Tracked Jaw Crusher Plant model data
| Model | MJ150SE | MJ260E | MJ-350E | MJ-450SE |
|---|---|---|---|---|
| Feeder | ||||
| Volume(m³) | 4 | 6 | 6 | 6 |
| Feeding height(mm) | 3500 | 4357 | 4357 | 4357 |
| Maximum feed size(mm) | 430 | 560 | 630 | 720 |
| Crusher | ||||
| Host model | MC80 | MC106 | MC113 | MC120 |
| Feed opening(mm) | 800×510 | 1060X700 | 1130×750 | 1200×870 |
| Closed side setting(mm) | 40-175 | 70-200 | 70-200 | 70-200 |
Take productivity to the next level with the HMC Series Tracked Jaw Crusher Plant. Read the table column by column against mine pre-beneficiation feed: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a greenfield site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | tight grading compliance |
| Evaluation horizon | single-project view |
| Site condition | a greenfield site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for tracked jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.

From enquiry to the first saleable tonne
- Book shipping, prepare the packing list and confirm the container loading plan.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
Shortening this sequence is possible on a greenfield site, but only where the feed and product specification are already fully defined.
What to verify before you sign
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Local service partner, technician travel time and visa requirements for your market.
- Liner alloy: Mn22 matched to the rock, not to the lowest purchase price.
- Decommissioning or relocation value at the end of a single-project horizon.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Control system language, telemetry and remote diagnostics availability.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Using one liner profile for both secondary and tertiary stages.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Buying tight grading compliance on price alone and losing it in availability.
On a greenfield site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Check lubrication levels, grease lines and oil cooler operation.
- Verify rotation direction on every motor before coupling.
- Dry-run the plant empty for the specified period and record vibration.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Calibrate the belt scale and any level probes against a known load.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check belt tracking, chute build-up and transfer-point dust.
Keep the signed record; it is the only defensible baseline for later performance disputes.