Overview
A laboratory measure of the energy needed to reduce a rock from a theoretically infinite size to a defined product size, expressed in kWh per tonne.

Why it matters in practice
- Used to size motors and predict power
- Hard abrasive rock has a high value
- Measured by standard Bond ball/rod mill tests
Applying it to plant selection
Engineers use bond work index together with feed gradation, moisture content and target tonnage when fixing the flow sheet. HAMAC records the value in the project data sheet so the equipment list, liner grade and motor rating can be checked against the written performance guarantee.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | seven-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | simple operator maintenance |
| Evaluation horizon | seven-year view |
| Site condition | a brownfield extension |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.
What to verify before you sign
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Guaranteed power draw and the simple operator maintenance trade-off it implies.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Whether the quoted t/h is achieved at seasonal road-project supply or under ideal laboratory feed.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a brownfield extension.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Assuming the manufacturer's warranty covers wear parts and consumables.
For seasonal road-project supply, protect the simple operator maintenance requirement explicitly in the contract documents.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Test emergency stops, pull wires and interlock trips in sequence.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Sample each product fraction and compare with the specification.
- Measure noise and dust at the operator position against the local limit.
- Confirm the direction and tension of every belt under no load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Dry-run the plant empty for the specified period and record vibration.
The commissioning record becomes the reference for every liner change in the seven-year plan.