Overview
Quarries in Egypt typically process Limestone, Granite. The plant is sized to saleable tonnes per hour across 0–5, 5–10, 10–20 and 20–31.5 mm fractions rather than to crusher nameplate.

Scope of supply
- Primary jaw sized for the maximum feed lump.
- Secondary cone or impact matched to rock hardness.
- Multi-deck screens with adequate area for the fines fraction.
- Surge bin and controlled feed for consistent chamber load.
- Dust suppression and haul-road planning.
Market parameters for Egypt
| Item | Reference |
|---|---|
| Region | Africa |
| Port | Alexandria |
| Voltage / frequency | 380V 50Hz |
| Standards | EOS |
| Typical feed | Limestone, Granite |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Alexandria |
| Site supply | 380V 50Hz |
| Local standards | EOS |
| Region | Africa |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | single-project view |
At mine pre-beneficiation feed, the ranking of these parameters changes: strict product cubicity usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | strict product cubicity |
| Evaluation horizon | single-project view |
| Site condition | a coastal export terminal |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.
What to verify before you sign
- Choke-feed arrangement: surge bin, feeder control and level indication.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Liner alloy: high-chrome iron matched to the rock, not to the lowest purchase price.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Local service partner, technician travel time and visa requirements for Egypt.
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Wear-part interchangeability across machines in the same circuit.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a coastal export terminal.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Using one liner profile for both secondary and tertiary stages.
Review the list with a rotating shift crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Confirm the direction and tension of every belt under no load.
- Calibrate the belt scale and any level probes against a known load.
- Record the baseline grading curve for each product fraction.
- Test emergency stops, pull wires and interlock trips in sequence.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Hand over the spare-parts list, manuals and maintenance schedule.
For a rotating shift crew, run through this list twice — once with the supervisor and once without.