Overview
Practical, numbers-first guidance on the Mobile 4 In 1 Crushing & Screening Plant — written for engineers specifying, buying and running crushing plants.

Abnormal noise / vibration
- Check for loose liner bolts or foreign metal in feed.
- Verify foundation bolts and coupling alignment.
- Listen for bearing distress; schedule replacement.
Low output
- Worn liners / blow bars reduce reduction.
- Wrong CSS / setting for target product.
- Screen blinding limits throughput.
Poor product shape
- Increase reduction in the shaping stage.
- Verify VSI rotor speed / anvil.
- Re-check screen mesh.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Mobile 4 In 1 Crushing & Screening Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | single-project view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published Mobile 4 In 1 Crushing & Screening Plant model data
| Model | Vibrating Feeder | Jaw Crusher | Cone Crusher / Impact Crusher | Vibrating Screen |
|---|---|---|---|---|
| Y3SY9E46 | GZD850×3000 | PE400×600 | PYB900 | 3YZS1237 |
| Y3SC75E57 | GZD850×3000 | PE500×700 | 3FT | 3YZS1548 |
| Y3SF1210E57 | GZD850×3000 | PE500×700 | PF1210 | 3YZS1548 |
| Y2SY9E57 | GZD850×3000 | PE500×700 | PYB900 | 2YZS1237 |
| Y3SF1010E46 | GZD850×3000 | PE400×600 | PF1010 | 3YZS1237 |
The 4-in-1 Mobile Crushing Plant combines a vibrating feeder, jaw crusher, cone or impact crusher, and vibrating screen in a single frame, offering an economical solution for mobile crushing. Read the table column by column against seasonal road-project supply: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a coastal export terminal in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | single-project view |
| Site condition | a coastal export terminal |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for mobile 4 in 1 crushing & screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Plan training for a mixed local and expatriate team on CSS adjustment, liner change-out and lock-out / tag-out.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.

What to verify before you sign
- Local service partner, technician travel time and visa requirements for your market.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Guaranteed power draw and the lowest energy per tonne trade-off it implies.
- Control system language, telemetry and remote diagnostics availability.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Dust and noise control designed to the local emission limits for your market.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On seasonal road-project supply, the lowest energy per tonne objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Letting the seasonal road-project supply duty be defined verbally instead of in the contract.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Hand over the spare-parts list, manuals and maintenance schedule.
- Verify rotation direction on every motor before coupling.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Record the baseline grading curve for each product fraction.
- Check belt tracking, chute build-up and transfer-point dust.
- Dry-run the plant empty for the specified period and record vibration.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
For a mixed local and expatriate team, run through this list twice — once with the supervisor and once without.