Overview
Practical, numbers-first guidance on the Screw Type Sand Washing Machine — written for engineers specifying, buying and running crushing plants.

Preparation
- Confirm foundation per HAMAC layout.
- Check power and cable routing.
- Lift and level on grout.
Commissioning
- Dry run, then graded load.
- Set CSS and verify product.
- Train operators.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Screw Type Sand Washing Machine |
| Category | Supporting Equipments |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | seven-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published Screw Type Sand Washing Machine model data
| Model | Diameter of spiral (mm) | Width of washing tank (mm) | Feeding size (mm) | Spiral rotation speed (r/min) |
|---|---|---|---|---|
| LXS-515 | 515 | 6715 | ≤10 | 38 |
| LXS-765 | 765 | 7620 | ≤10 | 26 |
| LXS-915 | 915 | 7650 | ≤10 | 21 |
| LXS-1115 | 1115 | 9782 | ≤10 | 17 |
| 2LXS-915 | 915 | 7650 | ≤10 | 21 |
| 2LXS-1115 | 1115 | 9782 | ≤10 | 17 |
The high-efficiency screw type sand washing machine is widely used in industries such as highways and hydropower to clean, dewater, and grade sand and gravel materials. Read the table column by column against manufactured-sand production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a coastal export terminal in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | simple operator maintenance |
| Evaluation horizon | seven-year view |
| Site condition | a coastal export terminal |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for screw type sand washing machine may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Book shipping, prepare the packing list and confirm the container loading plan.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Whether the quoted t/h is achieved at manufactured-sand production or under ideal laboratory feed.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Local service partner, technician travel time and visa requirements for your market.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Buying simple operator maintenance on price alone and losing it in availability.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
On a coastal export terminal, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Verify rotation direction on every motor before coupling.
- Confirm the direction and tension of every belt under no load.
- Check lubrication levels, grease lines and oil cooler operation.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Record power draw, tonnage and chamber pressure at steady state.
Keep the signed record; it is the only defensible baseline for later performance disputes.