Overview
Basalt (Mohs 6, ~200 MPa, high abrasion): processing steps, equipment and cost notes for plant buyers.

Processing steps
- Primary crushing — jaw.
- Secondary / tertiary — jaw + cone + VSI.
- Screening for graded products.
- Dewatering / handling.
Recommended equipment
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
- VSI Vertical Shaft Impact Crusher (Sand Making Machine)
Cost notes
Operating cost is dominated by wear parts on high-abrasion material; choose liner grade by rock, not price.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Basalt |
| Mohs hardness | 6 |
| Compressive strength | ~200 MPa |
| Abrasiveness | High |
| Recommended circuit | jaw + cone + VSI |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | single-project view |
Ask for the same table from any competing supplier; without it, an offer for basalt crushing cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | fast mobilisation |
| Evaluation horizon | single-project view |
| Site condition | a remote mine site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for basalt crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Review the crusher chamber profile with the liner supplier against Basalt (Mohs 6, ~200 MPa, high abrasion).
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Book shipping, prepare the packing list and confirm the container loading plan.
On contract crushing on short-term sites, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Product sampling points and the lab equipment needed for routine grading checks.
- Control system language, telemetry and remote diagnostics availability.
- Written performance guarantee, sampling method and acceptance-test protocol.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 20% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 6% | kWh per tonne, local tariff and dust suppression water |
Freight to your market is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Measure noise and dust at the operator position against the local limit.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Record power draw, tonnage and chamber pressure at steady state.
- Check lubrication levels, grease lines and oil cooler operation.
- Calibrate the belt scale and any level probes against a known load.
- Confirm the direction and tension of every belt under no load.
- Hand over the spare-parts list, manuals and maintenance schedule.
For a mixed local and expatriate team, run through this list twice — once with the supervisor and once without.