Overview
Published Mobile Impact Crusher Plant specifications below are nominal values transcribed from HAMAC data. Actual performance depends on feed gradation, moisture, setting and screening efficiency.

Specification table
| Parameter | Value |
|---|---|
| Weighing (kg) | 28800 31500 |
| Impact crusher | |
| Model | PF1210 PF1214 |
| Feed opening (mm) | 400*1080 400*1430 |
| Nominal capacity (t/h) | 70-130 100-180 |
| Vibrating feeder | |
| Model | ZZG3895 ZZG4211 |
How to read the data
- Rated capacity is at a specified CSS / setting and material — treat it as saleable product, not crusher throughput.
- Feed size limit protects the chamber; oversize feed causes bridging.
- Motor power scales with rotor / chamber size, not linearly with capacity.
Selecting the right model
Match the model to your target t/h at the required product size, then confirm with a HAMAC engineer before order.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Mobile Impact Crusher Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | single-project view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published Mobile Impact Crusher Plant model data
| Model | MHSI1210 | MHSI1214 | MHSI1315 |
|---|---|---|---|
| Weighing (kg) | 28800 | 31500 | 39600 |
| Impact crusher | |||
| Model | PF1210 | PF1214 | PF1315 |
| Feed opening (mm) | 400*1080 | 400*1430 | 860*1520 |
| Nominal capacity (t/h) | 70-130 | 100-180 | 130-250 |
| Vibrating feeder | |||
| Model | ZZG3895 | ZZG4211 | ZZG4911 |
| Belt conveyor |
Mobile impact crusher plant is a versatile, efficient, and easy-to-move crushing machine designed for rock and material size reduction in aggregates production, recycling, and mining. Read the table column by column against mine pre-beneficiation feed: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a greenfield site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | simple operator maintenance |
| Evaluation horizon | single-project view |
| Site condition | a greenfield site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for mobile impact crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Confirm the haul-road and stockpile plan with a greenfield site in mind before fixing conveyor lengths.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Decommissioning or relocation value at the end of a single-project horizon.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Guaranteed power draw and the simple operator maintenance trade-off it implies.
- Wear-part interchangeability across machines in the same circuit.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Control system language, telemetry and remote diagnostics availability.
For mine pre-beneficiation feed, give the simple operator maintenance line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a greenfield site.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
For mine pre-beneficiation feed, protect the simple operator maintenance requirement explicitly in the contract documents.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Confirm the direction and tension of every belt under no load.
- Check lubrication levels, grease lines and oil cooler operation.
- Record power draw, tonnage and chamber pressure at steady state.
- Dry-run the plant empty for the specified period and record vibration.
- Check belt tracking, chute build-up and transfer-point dust.
On a greenfield site, allow extra time for the dust and noise measurements.