Overview
Practical, numbers-first guidance on the Tracked Vibrating Screening Plant — written for engineers specifying, buying and running crushing plants.

Capacity factors
- Chamber / CSS and material.
- Feed gradation and moisture.
- Screen efficiency downstream.
- Continuous vs surge feed.
Rule of thumb
Rated capacity is stated at a given CSS and material; treat it as saleable product, not crusher throughput. Size the plant to 10–20% above target.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Tracked Vibrating Screening Plant |
| Category | Tracked Crushing Plants |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | three-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and three-year operating plan.
Published Tracked Vibrating Screening Plant model data
| Model | MS-3618E |
|---|---|
| Feeder | |
| Volume | 2.8 m³ |
| Feeding height | 2288 mm |
| Maximum feed size | 200 mm |
| Feeding capacity | 350 t/h |
| Screening | |
| Vibrating screen length×width | 1800 x 6000 mm |
| Number of layers | 3 |
Maximize productivity with the HMC series Tracked Vibrating Screening Plant. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | three-year view |
| Site condition | a remote mine site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for tracked vibrating screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Product sampling points and the lab equipment needed for routine grading checks.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Wear-part interchangeability across machines in the same circuit.
- Dust and noise control designed to the local emission limits for your market.
- Guaranteed power draw and the maximum mechanical availability trade-off it implies.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On contract crushing on short-term sites, the maximum mechanical availability objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Using one liner profile for both secondary and tertiary stages.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
Review the list with a full-time plant team before the order is placed — they will recognise most of them.
Commissioning checklist
- Dry-run the plant empty for the specified period and record vibration.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure noise and dust at the operator position against the local limit.
- Calibrate the belt scale and any level probes against a known load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Verify rotation direction on every motor before coupling.
- Check lubrication levels, grease lines and oil cooler operation.
- Check belt tracking, chute build-up and transfer-point dust.
Keep the signed record; it is the only defensible baseline for later performance disputes.