Overview
Practical, numbers-first guidance on the Tracked Jaw Crusher Plant — written for engineers specifying, buying and running crushing plants.

Capacity factors
- Chamber / CSS and material.
- Feed gradation and moisture.
- Screen efficiency downstream.
- Continuous vs surge feed.
Rule of thumb
Rated capacity is stated at a given CSS and material; treat it as saleable product, not crusher throughput. Size the plant to 10–20% above target.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Tracked Jaw Crusher Plant |
| Category | Tracked Crushing Plants |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | five-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published Tracked Jaw Crusher Plant model data
| Model | MJ150SE | MJ260E | MJ-350E | MJ-450SE |
|---|---|---|---|---|
| Feeder | ||||
| Volume(m³) | 4 | 6 | 6 | 6 |
| Feeding height(mm) | 3500 | 4357 | 4357 | 4357 |
| Maximum feed size(mm) | 430 | 560 | 630 | 720 |
| Crusher | ||||
| Host model | MC80 | MC106 | MC113 | MC120 |
| Feed opening(mm) | 800×510 | 1060X700 | 1130×750 | 1200×870 |
| Closed side setting(mm) | 40-175 | 70-200 | 70-200 | 70-200 |
Take productivity to the next level with the HMC Series Tracked Jaw Crusher Plant. Read the table column by column against manufactured-sand production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a confined urban yard in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | fast mobilisation |
| Evaluation horizon | five-year view |
| Site condition | a confined urban yard |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for tracked jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Wear-part interchangeability across machines in the same circuit.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Control system language, telemetry and remote diagnostics availability.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
For tracked jaw crusher plant at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Buying fast mobilisation on price alone and losing it in availability.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Measure and log the as-new CSS / setting for future wear comparison.
- Dry-run the plant empty for the specified period and record vibration.
- Check lubrication levels, grease lines and oil cooler operation.
- Sample each product fraction and compare with the specification.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Verify rotation direction on every motor before coupling.
- Measure noise and dust at the operator position against the local limit.
- Record the baseline grading curve for each product fraction.
On a confined urban yard, allow extra time for the dust and noise measurements.