Overview
Wear parts dominate the running cost of a plant in Mexico. HAMAC holds matched liners, blow bars, screen meshes, belts, bearings and seals for every supplied model, shipped as consolidated consignments to Manzanillo.

Scope of supply
- One full set of chamber liners or blow bars per machine.
- Screen meshes for every deck and aperture.
- Drive belts, bearings, seals and hydraulic hoses.
- Electrical consumables and sensors.
- Documentation aligned with NOM for customs.
Market parameters for Mexico
| Item | Reference |
|---|---|
| Region | North America |
| Port | Manzanillo |
| Voltage / frequency | 460V 60Hz |
| Standards | NOM |
| Typical feed | Basalt, Limestone |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Manzanillo |
| Site supply | 460V 60Hz |
| Local standards | NOM |
| Region | North America |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | three-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | simple operator maintenance |
| Evaluation horizon | three-year view |
| Site condition | a coastal export terminal |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Mexico.
What to verify before you sign
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Control system language, telemetry and remote diagnostics availability.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Whether the quoted t/h is achieved at seasonal road-project supply or under ideal laboratory feed.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Dust and noise control designed to the local emission limits for Mexico.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Overlooking dust, noise and water permits in Mexico until erection has already started.
- Buying simple operator maintenance on price alone and losing it in availability.
On a coastal export terminal, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Record the baseline grading curve for each product fraction.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check lubrication levels, grease lines and oil cooler operation.
- Calibrate the belt scale and any level probes against a known load.
- Confirm all guards, emergency stops and pull-wire switches function.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Confirm the direction and tension of every belt under no load.
- Dry-run the plant empty for the specified period and record vibration.
Keep the signed record; it is the only defensible baseline for later performance disputes.