Overview
A turnkey contract covers the flow sheet, manufacture, shipment to Manzanillo, civil reference drawings, erection supervision, commissioning and operator training — one project manager from enquiry to hand-over.

Scope of supply
- Site survey and material testing.
- Flow sheet, layout and foundation reference.
- Manufacture, workshop assembly and load test.
- Freight and customs documentation for Mexico.
- Erection supervision, 460V 60Hz power tie-in and training.
Market parameters for Mexico
| Item | Reference |
|---|---|
| Region | North America |
| Port | Manzanillo |
| Voltage / frequency | 460V 60Hz |
| Standards | NOM |
| Typical feed | Basalt, Limestone |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Manzanillo |
| Site supply | 460V 60Hz |
| Local standards | NOM |
| Region | North America |
| Assumed duty | continuous quarry production |
| Evaluation horizon | three-year view |
Ask for the same table from any competing supplier; without it, an offer for the crushing and screening plant cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | three-year view |
| Site condition | a brownfield extension |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
A realistic programme reserves time for permits, foundation curing and shipping to Mexico before any steel is cut.
What to verify before you sign
- After-sales response time, technician availability and the warranty exclusions in writing.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Control system language, telemetry and remote diagnostics availability.
- Product sampling points and the lab equipment needed for routine grading checks.
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Decommissioning or relocation value at the end of a three-year horizon.
- Nameplate data for 460V 60Hz and the NOM certificate set.
- Local service partner, technician travel time and visa requirements for Mexico.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
Share this list with a full-time plant team as well as procurement; operators are the ones who live with the omissions.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A three-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Overlooking dust, noise and water permits in Mexico until erection has already started.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Omitting a bypass chute, so a single screen fault stops the whole line.
On a brownfield extension, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Calibrate the belt scale and any level probes against a known load.
- Confirm the direction and tension of every belt under no load.
- Check belt tracking, chute build-up and transfer-point dust.
- Test emergency stops, pull wires and interlock trips in sequence.
- Confirm all guards, emergency stops and pull-wire switches function.
- Record the baseline grading curve for each product fraction.
- Verify rotation direction on every motor before coupling.
On a brownfield extension, allow extra time for the dust and noise measurements.