Overview
Practical notes for bringing a HAMAC crushing or grinding plant into Mexico, from quotation to commissioning.

Shipping & port
- Destination: Manzanillo.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 460V 60Hz.
- Standards: NOM.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for Mexico customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Manzanillo |
| Site supply | 460V 60Hz |
| Local standards | NOM |
| Region | North America |
| Assumed duty | continuous quarry production |
| Evaluation horizon | three-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | three-year view |
| Site condition | an existing quarry bench |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
A realistic programme reserves time for permits, foundation curing and shipping to Mexico before any steel is cut.

What to verify before you sign
- After-sales response time, technician availability and the warranty exclusions in writing.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Decommissioning or relocation value at the end of a three-year horizon.
- Dust and noise control designed to the local emission limits for Mexico.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Nameplate data for 460V 60Hz and the NOM certificate set.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the three-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A three-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Overlooking dust, noise and water permits in Mexico until erection has already started.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Buying lowest cost per tonne on price alone and losing it in availability.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
For continuous quarry production, protect the lowest cost per tonne requirement explicitly in the contract documents.
Commissioning checklist
- Verify rotation direction on every motor before coupling.
- Confirm all guards, emergency stops and pull-wire switches function.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Dry-run the plant empty for the specified period and record vibration.
- Record power draw, tonnage and chamber pressure at steady state.
- Test emergency stops, pull wires and interlock trips in sequence.
- Measure noise and dust at the operator position against the local limit.
The commissioning record becomes the reference for every liner change in the three-year plan.