Overview
This page brings together the published Mobile Jaw Crusher Plant model data and the practical details of importing it into Kenya — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Basalt.

Published Mobile Jaw Crusher Plant data
| Published parameter | Nominal value |
|---|---|
| MJ69 | 95-165 mm 30-85 m³/h |
| MJC96 | 60-175 mm 60-200 m³/h |
| MJ750 | 80-180 mm 72-150 m³/h |
| MJC106 | 70-200 mm 100-300 m³/h |
Local conditions in Kenya
- Destination port: Mombasa.
- Site supply: 415V 50Hz.
- Standards: KS.
- Common materials: Limestone, Basalt.
- Region: Africa.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Mombasa, sets motors and starters to 415V 50Hz, and supplies the certificate set applicable to KS. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Mombasa |
| Site supply | 415V 50Hz |
| Local standards | KS |
| Region | Africa |
| Machine line | Mobile Jaw Crusher Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | five-year view |
Treat this as a living sheet. Every revision of the flow sheet for Kenya should update the same fields so the equipment list stays traceable.
Published Mobile Jaw Crusher Plant model data
| Model | Discharge Adjustment | Nominal Capacity | Dimension | Magnetic Separator | Axles |
|---|---|---|---|---|---|
| MJ69 | 95-165 mm | 30-85 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJC96 | 60-175 mm | 60-200 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJ750 | 80-180 mm | 72-150 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
| MJC106 | 70-200 mm | 100-300 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
The tire-type mobilejaw crusher mobile is a mobile primary crushing equipment composed of vibratingfeeder, jaw crusher, conveyor belt and other components. Read the table column by column against demolition and recycling duties: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for an existing quarry bench in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | five-year view |
| Site condition | an existing quarry bench |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for mobile jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Book container or flat-rack space to Mombasa and prepare the customs document set in advance.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Specify motors, starters and documentation for 415V 50Hz and KS before manufacture.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
For a small contractor crew, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Decommissioning or relocation value at the end of a five-year horizon.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Product sampling points and the lab equipment needed for routine grading checks.
- Control system language, telemetry and remote diagnostics availability.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the five-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Letting the demolition and recycling duties duty be defined verbally instead of in the contract.
- Using one liner profile for both secondary and tertiary stages.
- Overlooking dust, noise and water permits in Kenya until erection has already started.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
On an existing quarry bench, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Test emergency stops, pull wires and interlock trips in sequence.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Dry-run the plant empty for the specified period and record vibration.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check lubrication levels, grease lines and oil cooler operation.
- Check belt tracking, chute build-up and transfer-point dust.
- Verify rotation direction on every motor before coupling.
Keep the signed record; it is the only defensible baseline for later performance disputes.