Overview
This page brings together the published PE Series Jaw Crusher model data and the practical details of importing it into Thailand — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Basalt.

Published PE Series Jaw Crusher data
| Published parameter | Nominal value |
|---|---|
| PEX250x750 | 250x750 mm 210 mm |
| PEX250x1000 | 250x1000 mm 210 mm |
| PEX250x1200 | 250x1200 mm 210 mm |
| PEX300x1300 | 300x1300 mm 250 mm |
| PE400×600 | 400×600 mm 340 mm |
| PE500×750 | 500×750 mm 425 mm |
Local conditions in Thailand
- Destination port: Laem Chabang.
- Site supply: 380V 50Hz.
- Standards: TISI.
- Common materials: Limestone, Basalt.
- Region: Asia.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Laem Chabang, sets motors and starters to 380V 50Hz, and supplies the certificate set applicable to TISI. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Laem Chabang |
| Site supply | 380V 50Hz |
| Local standards | TISI |
| Region | Asia |
| Machine line | PE Series Jaw Crusher |
| Category | Jaw Crusher |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | seven-year view |
These values are the starting point for a written proposal on pe series jaw crusher; they are nominal and should be confirmed against a sample test before manufacture.
Published PE Series Jaw Crusher model data
| Model | Input Size | Max Feeding Size | Output Range | Capacity | Engine Power | Weight |
|---|---|---|---|---|---|---|
| PEX250x750 | 250x750 mm | 210 mm | 25-60 mm | 13-35 T/H | 30 KW | 5.5 T |
| PEX250x1000 | 250x1000 mm | 210 mm | 25-60 mm | 16-52 T/H | 37 KW | 7 T |
| PEX250x1200 | 250x1200 mm | 210 mm | 25-60 mm | 20-61 T/H | 55 KW | 9.5 T |
| PEX300x1300 | 300x1300 mm | 250 mm | 20-90 mm | 16-105 T/H | 75 KW | 15.6 T |
| PE400×600 | 400×600 mm | 340 mm | 40-100 mm | 16-60 T/H | 30 KW | 6.7 T |
| PE500×750 | 500×750 mm | 425 mm | 50-100 mm | 40-110 T/H | 55 KW | 11.7 T |
| PE600×900 | 600×900 mm | 500 mm | 65-180 mm | 80-180 T/H | 55-75 KW | 16.1 T |
| PE750×1060 | 750×1060 mm | 630 mm | 80-180 mm | 110-320 T/H | 90-110 KW | 30.1 T |
Jaw crushers are often used for primary crushing in mine material crushing. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a confined urban yard in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | tight grading compliance |
| Evaluation horizon | seven-year view |
| Site condition | a confined urban yard |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for pe series jaw crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Book container or flat-rack space to Laem Chabang and prepare the customs document set in advance.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Local service partner, technician travel time and visa requirements for Thailand.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Wear-part interchangeability across machines in the same circuit.
- Guaranteed power draw and the tight grading compliance trade-off it implies.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Overlooking dust, noise and water permits in Thailand until erection has already started.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Using one liner profile for both secondary and tertiary stages.
- Omitting a bypass chute, so a single screen fault stops the whole line.
For contract crushing on short-term sites, protect the tight grading compliance requirement explicitly in the contract documents.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Measure and log the as-new CSS / setting for future wear comparison.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Check lubrication levels, grease lines and oil cooler operation.
- Record power draw, tonnage and chamber pressure at steady state.
- Check belt tracking, chute build-up and transfer-point dust.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Test emergency stops, pull wires and interlock trips in sequence.
The commissioning record becomes the reference for every liner change in the seven-year plan.