Overview
This page brings together the published Mobile Jaw Crusher Plant model data and the practical details of importing it into Iran — power supply, standards, shipping and commissioning. Popular feed materials in the market include Copper ore, Limestone.

Published Mobile Jaw Crusher Plant data
| Published parameter | Nominal value |
|---|---|
| MJ69 | 95-165 mm 30-85 m³/h |
| MJC96 | 60-175 mm 60-200 m³/h |
| MJ750 | 80-180 mm 72-150 m³/h |
| MJC106 | 70-200 mm 100-300 m³/h |
Local conditions in Iran
- Destination port: Bandar Abbas.
- Site supply: 380V 50Hz.
- Standards: ISIRI.
- Common materials: Copper ore, Limestone.
- Region: Middle East.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Bandar Abbas, sets motors and starters to 380V 50Hz, and supplies the certificate set applicable to ISIRI. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Bandar Abbas |
| Site supply | 380V 50Hz |
| Local standards | ISIRI |
| Region | Middle East |
| Machine line | Mobile Jaw Crusher Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | three-year view |
Use the table as a checklist when comparing quotations for mobile jaw crusher plant — a lower price often means one of these parameters was quietly reduced.
Published Mobile Jaw Crusher Plant model data
| Model | Discharge Adjustment | Nominal Capacity | Dimension | Magnetic Separator | Axles |
|---|---|---|---|---|---|
| MJ69 | 95-165 mm | 30-85 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJC96 | 60-175 mm | 60-200 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJ750 | 80-180 mm | 72-150 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
| MJC106 | 70-200 mm | 100-300 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
The tire-type mobilejaw crusher mobile is a mobile primary crushing equipment composed of vibratingfeeder, jaw crusher, conveyor belt and other components. Read the table column by column against cement raw-meal preparation: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | fast mobilisation |
| Evaluation horizon | three-year view |
| Site condition | a remote mine site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for mobile jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Book container or flat-rack space to Bandar Abbas and prepare the customs document set in advance.
Shortening this sequence is possible on a remote mine site, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Wear-part interchangeability across machines in the same circuit.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Nameplate data for 380V 50Hz and the ISIRI certificate set.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Dust and noise control designed to the local emission limits for Iran.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
For mobile jaw crusher plant at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Overlooking dust, noise and water permits in Iran until erection has already started.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Buying fast mobilisation on price alone and losing it in availability.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Omitting a bypass chute, so a single screen fault stops the whole line.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Dry-run the plant empty for the specified period and record vibration.
- Verify rotation direction on every motor before coupling.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Confirm the direction and tension of every belt under no load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
Keep the signed record; it is the only defensible baseline for later performance disputes.