Overview
This page brings together the published PF Impact Crusher model data and the practical details of importing it into Peru — power supply, standards, shipping and commissioning. Popular feed materials in the market include Copper ore, Gold ore.

Published PF Impact Crusher data
| Published parameter | Nominal value |
|---|---|
| PF-1007 | Φ1000×700 mm 400×730 mm |
| PF-1010 | Φ1000×1050 mm 400×1080 mm |
| PF-1210 | Φ1250×1050 mm 400×1080 mm |
| PF-1214 | Φ1250×1400 mm 400×1430 mm |
| PF-1315 | Φ1320×1500 mm 860×1520 mm |
| PF-1520 | Φ1500×2000 mm 830×2040 mm |
Local conditions in Peru
- Destination port: Callao.
- Site supply: 380V 60Hz.
- Standards: NTP.
- Common materials: Copper ore, Gold ore.
- Region: South America.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Callao, sets motors and starters to 380V 60Hz, and supplies the certificate set applicable to NTP. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Callao |
| Site supply | 380V 60Hz |
| Local standards | NTP |
| Region | South America |
| Machine line | PF Impact Crusher |
| Category | Impact Crusher |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | ten-year view |
At mine pre-beneficiation feed, the ranking of these parameters changes: minimal civil works usually becomes the deciding constraint rather than the headline tonnage.
Published PF Impact Crusher model data
| Model | Rotor size | Feed opening | Max. Feeding size | Capacity | Motor Power | Weight | Overall dimension |
|---|---|---|---|---|---|---|---|
| PF-1007 | Φ1000×700 mm | 400×730 mm | 300 mm | 30-70 t/h | 37-45 kW | 12 t | 2330×1660×2300 mm |
| PF-1010 | Φ1000×1050 mm | 400×1080 mm | 350 mm | 50-90 t/h | 45-55 kW | 15 t | 2370×1700×2390 mm |
| PF-1210 | Φ1250×1050 mm | 400×1080 mm | 350 mm | 70-130 t/h | 110 kW | 17.7 t | 2680×2160×2800 mm |
| PF-1214 | Φ1250×1400 mm | 400×1430 mm | 350 mm | 100-180 t/h | 132 kW | 22.4 t | 2650×2460×2800 mm |
| PF-1315 | Φ1320×1500 mm | 860×1520 mm | 500 mm | 130-250 t/h | 220 kW | 27 t | 3180×2720×2620 mm |
| PF-1520 | Φ1500×2000 mm | 830×2040 mm | 700 mm | 300-550 t/h | 315-400 kW | 50.6 t | 3959×3564×3330 mm |
| PF-1620 | Φ1600×2000 mm | 2000×1600 mm | 500 mm | 400-700 t/h | 400-500 kW | 58 t | 4259×3660×3450 mm |
| PF-1820 | Φ1800×2000 mm | 1260×2040 mm | 800 mm | 600-800 t/h | 630-710 kW | 83.21 t | 4400×3866×4009 mm |
The impact crusher (impact crusher) is a new generation of impact crusher developed in combination with the specific working conditions of the sand and gravel. Read the table column by column against mine pre-beneficiation feed: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a confined urban yard in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | minimal civil works |
| Evaluation horizon | ten-year view |
| Site condition | a confined urban yard |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for pf impact crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Specify motors, starters and documentation for 380V 60Hz and NTP before manufacture.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
A realistic programme reserves time for permits, foundation curing and shipping to Peru before any steel is cut.

What to verify before you sign
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Guaranteed power draw and the minimal civil works trade-off it implies.
- Control system language, telemetry and remote diagnostics availability.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Availability of an owner-operator team for liner changes and the lifting equipment on site.
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
On mine pre-beneficiation feed, the minimal civil works objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Overlooking dust, noise and water permits in Peru until erection has already started.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
Review the list with an owner-operator team before the order is placed — they will recognise most of them.
Commissioning checklist
- Check lubrication levels, grease lines and oil cooler operation.
- Verify rotation direction on every motor before coupling.
- Measure noise and dust at the operator position against the local limit.
- Confirm the direction and tension of every belt under no load.
- Record the baseline grading curve for each product fraction.
- Calibrate the belt scale and any level probes against a known load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
On a confined urban yard, allow extra time for the dust and noise measurements.