Overview
Iron ore (Mohs 5.5, ~160 MPa) is processed in India for aggregates, ore or industrial minerals. HAMAC configures the circuit to local conditions: Mumbai, 415V 50Hz, BIS.

Iron ore properties
| Property | Value |
|---|---|
| Mohs | 5.5 |
| Compressive strength | 160 MPa |
| Abrasion | Medium |
| Circuit | jaw + cone (+ HPGR option) |
In India
- Port: Mumbai.
- Power: 415V 50Hz.
- Standards: BIS.
Equipment
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
- Symons Cone Crusher
Budget
Send material, capacity and product sizes for a configured FOB/CIF budget to Mumbai.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Iron ore |
| Mohs hardness | 5.5 |
| Compressive strength | ~160 MPa |
| Abrasiveness | Medium |
| Recommended circuit | jaw + cone (+ HPGR option) |
| Destination port | Mumbai |
| Site supply | 415V 50Hz |
| Local standards | BIS |
| Region | Asia |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | three-year view |
The figures above are transcribed from published HAMAC data and from the material properties of iron ore; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | minimal civil works |
| Evaluation horizon | three-year view |
| Site condition | a confined urban yard |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for iron ore crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
- Book container or flat-rack space to Mumbai and prepare the customs document set in advance.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Review the crusher chamber profile with the liner supplier against Iron ore (Mohs 5.5, ~160 MPa, medium abrasion).
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
On mine pre-beneficiation feed, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.

What to verify before you sign
- Control system language, telemetry and remote diagnostics availability.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Dust and noise control designed to the local emission limits for India.
- Availability of an owner-operator team for liner changes and the lifting equipment on site.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Local service partner, technician travel time and visa requirements for India.
- Product sampling points and the lab equipment needed for routine grading checks.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 50% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 17% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Dry-run the plant empty for the specified period and record vibration.
- Test emergency stops, pull wires and interlock trips in sequence.
- Verify rotation direction on every motor before coupling.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Confirm all guards, emergency stops and pull-wire switches function.
- Confirm the direction and tension of every belt under no load.
- Record power draw, tonnage and chamber pressure at steady state.
- Calibrate the belt scale and any level probes against a known load.
The commissioning record becomes the reference for every liner change in the three-year plan.