Overview
Single-size, high-PSV, low-flakiness aggregate. In Chile the most frequently processed feed materials are Copper ore, Basalt, and equipment is normally delivered through Valparaíso on 380V 50Hz supplies.

Materials in scope
- Basalt — Mohs 6, ~200 MPa, high abrasion
- Granite — Mohs 6.5, ~180 MPa, high abrasion
- Andesite — Mohs 6, ~170 MPa, high abrasion
Recommended machines
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
- VSI Vertical Shaft Impact Crusher (Sand Making Machine)
Engineering for Chile
| Item | Reference |
|---|---|
| Port | Valparaíso |
| Power | 380V 50Hz |
| Standards | NCh |
| Region | South America |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Valparaíso |
| Site supply | 380V 50Hz |
| Local standards | NCh |
| Region | South America |
| Application | Road & Railway Ballast |
| Typical feed | Basalt, Granite, Andesite |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | seven-year view |
At high-tonnage aggregate supply, the ranking of these parameters changes: lowest cost per tonne usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | seven-year view |
| Site condition | a brownfield extension |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Specify motors, starters and documentation for 380V 50Hz and NCh before manufacture.
- Book container or flat-rack space to Valparaíso and prepare the customs document set in advance.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Wear-part interchangeability across machines in the same circuit.
- Liner alloy: high-chrome iron matched to the rock, not to the lowest purchase price.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Written performance guarantee, sampling method and acceptance-test protocol.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Overlooking dust, noise and water permits in Chile until erection has already started.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
For high-tonnage aggregate supply, protect the lowest cost per tonne requirement explicitly in the contract documents.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Sample each product fraction and compare with the specification.
- Test emergency stops, pull wires and interlock trips in sequence.
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Record power draw, tonnage and chamber pressure at steady state.
- Check lubrication levels, grease lines and oil cooler operation.
Keep the signed record; it is the only defensible baseline for later performance disputes.
