Overview
Two-stage crushing then raw grinding to kiln feed. In India the most frequently processed feed materials are Granite, Limestone, Iron ore, and equipment is normally delivered through Mumbai on 415V 50Hz supplies.

Materials in scope
- Limestone — Mohs 3, ~100 MPa, low abrasion
- Gypsum — Mohs 1.5, ~30 MPa, low abrasion
- Bauxite — Mohs 2, ~50 MPa, low abrasion
Recommended machines
- PE Series Jaw Crusher
- PF Impact Crusher
- Mobile Impact Crusher Plant
- Vibrating Feeder
- Vibrating Screen
Engineering for India
| Item | Reference |
|---|---|
| Port | Mumbai |
| Power | 415V 50Hz |
| Standards | BIS |
| Region | Asia |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Mumbai |
| Site supply | 415V 50Hz |
| Local standards | BIS |
| Region | Asia |
| Application | Cement & Raw Meal |
| Typical feed | Limestone, Gypsum, Bauxite |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | seven-year view |
These values are the starting point for a written proposal on the crushing and screening plant; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | minimal civil works |
| Evaluation horizon | seven-year view |
| Site condition | a remote mine site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Specify motors, starters and documentation for 415V 50Hz and BIS before manufacture.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Book container or flat-rack space to Mumbai and prepare the customs document set in advance.
Shortening this sequence is possible on a remote mine site, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Product sampling points and the lab equipment needed for routine grading checks.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Wear-part interchangeability across machines in the same circuit.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Closed-side setting range and whether automatic setting regulation is included.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Using one liner profile for both secondary and tertiary stages.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Record power draw, tonnage and chamber pressure at steady state.
- Test emergency stops, pull wires and interlock trips in sequence.
- Measure and log the as-new CSS / setting for future wear comparison.
- Verify rotation direction on every motor before coupling.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
The commissioning record becomes the reference for every liner change in the seven-year plan.