Overview
A 50–100 tph crushing plant is a common size for Turkey. Main machines: PE jaw + PF impact / cone + 2-deck screen. Small quarries and concrete plants.

Main equipment
- PE jaw + PF impact / cone + 2-deck screen
- Shipped to Istanbul.
- Configured to 380V 50Hz / TS EN.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Turkey
- Port: Istanbul.
- Voltage: 380V 50Hz.
- Standards: TS EN.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 50–100 t/h |
| Typical main line | PE jaw + PF impact / cone + 2-deck screen |
| Scale note | Small quarries and concrete plants. |
| Destination port | Istanbul |
| Site supply | 380V 50Hz |
| Local standards | TS EN |
| Region | Europe/Asia |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | five-year view |
At mine pre-beneficiation feed, the ranking of these parameters changes: maximum mechanical availability usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | five-year view |
| Site condition | a coastal export terminal |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Specify motors, starters and documentation for 380V 50Hz and TS EN before manufacture.
For an owner-operator team, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Product sampling points and the lab equipment needed for routine grading checks.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Local service partner, technician travel time and visa requirements for Turkey.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for 50–100 t/h.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- After-sales response time, technician availability and the warranty exclusions in writing.
Share this list with an owner-operator team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 50% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Assuming the manufacturer's warranty covers wear parts and consumables.
For mine pre-beneficiation feed, protect the maximum mechanical availability requirement explicitly in the contract documents.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Confirm all guards, emergency stops and pull-wire switches function.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Confirm the direction and tension of every belt under no load.
- Calibrate the belt scale and any level probes against a known load.
- Measure noise and dust at the operator position against the local limit.
- Dry-run the plant empty for the specified period and record vibration.
Keep the signed record; it is the only defensible baseline for later performance disputes.