Overview
A 500–800 tph plant for gabbro (Mohs 6, ~180 MPa, high abrasion). Recommended circuit: jaw + cone.

Gabbro at this scale
| Capacity | 500–800 t/h |
|---|---|
| Material | Gabbro (High abrasion) |
| Circuit | jaw + cone |
Equipment
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
Notes
Massive, abrasive; premium liners.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Gabbro |
| Mohs hardness | 6 |
| Compressive strength | ~180 MPa |
| Abrasiveness | High |
| Recommended circuit | jaw + cone |
| Design capacity | 500–800 t/h |
| Typical main line | dual primary + multi-cone |
| Scale note | Large quarry / mine feed. |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | single-project view |
Treat this as a living sheet. Every revision of the flow sheet for your market should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | fast mobilisation |
| Evaluation horizon | single-project view |
| Site condition | a remote mine site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for gabbro crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Size the primary stage for 500–800 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Review the crusher chamber profile with the liner supplier against Gabbro (Mohs 6, ~180 MPa, high abrasion).
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Lay out the dual primary + multi-cone arrangement with straight conveyor runs and crane access for liner changes.
Shortening this sequence is possible on a remote mine site, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Decommissioning or relocation value at the end of a single-project horizon.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Control system language, telemetry and remote diagnostics availability.
- Local service partner, technician travel time and visa requirements for your market.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Written performance guarantee, sampling method and acceptance-test protocol.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 19% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 6% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Omitting a bypass chute, so a single screen fault stops the whole line.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Check lubrication levels, grease lines and oil cooler operation.
- Measure and log the as-new CSS / setting for future wear comparison.
- Dry-run the plant empty for the specified period and record vibration.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Confirm all guards, emergency stops and pull-wire switches function.
- Confirm the direction and tension of every belt under no load.
- Measure noise and dust at the operator position against the local limit.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
For a small contractor crew, run through this list twice — once with the supervisor and once without.