Overview
A 100–200 tph crushing plant is a common size for Pakistan. Main machines: PE/PEW jaw + cone + 3-deck screen. Most common export plant size.

Main equipment
- PE/PEW jaw + cone + 3-deck screen
- Shipped to Karachi.
- Configured to 400V 50Hz / PSQCA.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Pakistan
- Port: Karachi.
- Voltage: 400V 50Hz.
- Standards: PSQCA.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 100–200 t/h |
| Typical main line | PE/PEW jaw + cone + 3-deck screen |
| Scale note | Most common export plant size. |
| Destination port | Karachi |
| Site supply | 400V 50Hz |
| Local standards | PSQCA |
| Region | Asia |
| Assumed duty | continuous quarry production |
| Evaluation horizon | seven-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | fast mobilisation |
| Evaluation horizon | seven-year view |
| Site condition | a remote mine site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Specify motors, starters and documentation for 400V 50Hz and PSQCA before manufacture.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Lay out the PE/PEW jaw + cone + 3-deck screen arrangement with straight conveyor runs and crane access for liner changes.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
Shortening this sequence is possible on a remote mine site, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Closed-side setting range and whether automatic setting regulation is included.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for 100–200 t/h.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Dust and noise control designed to the local emission limits for Pakistan.
- Nameplate data for 400V 50Hz and the PSQCA certificate set.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Whether the quoted t/h is achieved at continuous quarry production or under ideal laboratory feed.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Liner alloy: high-chrome iron matched to the rock, not to the lowest purchase price.
Share this list with a rotating shift crew as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
Review the list with a rotating shift crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure and log the as-new CSS / setting for future wear comparison.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Sample each product fraction and compare with the specification.
- Measure noise and dust at the operator position against the local limit.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
Keep the signed record; it is the only defensible baseline for later performance disputes.