Overview
A 300–500 tph crushing plant is a common size for Mongolia. Main machines: primary gyratory/jaw + cone train. Commercial aggregate production.

Main equipment
- primary gyratory/jaw + cone train
- Shipped to Tianjin.
- Configured to 380V 50Hz / MNS.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Mongolia
- Port: Tianjin.
- Voltage: 380V 50Hz.
- Standards: MNS.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 300–500 t/h |
| Typical main line | primary gyratory/jaw + cone train |
| Scale note | Commercial aggregate production. |
| Destination port | Tianjin |
| Site supply | 380V 50Hz |
| Local standards | MNS |
| Region | Asia |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | single-project view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and single-project operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | tight grading compliance |
| Evaluation horizon | single-project view |
| Site condition | a brownfield extension |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Review the crusher chamber profile with the liner supplier against the feed material.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Confirm the haul-road and stockpile plan with a brownfield extension in mind before fixing conveyor lengths.
- Lay out the primary gyratory/jaw + cone train arrangement with straight conveyor runs and crane access for liner changes.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Specify motors, starters and documentation for 380V 50Hz and MNS before manufacture.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Guaranteed power draw and the tight grading compliance trade-off it implies.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Control system language, telemetry and remote diagnostics availability.
- Availability of an owner-operator team for liner changes and the lifting equipment on site.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the single-project review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Buying tight grading compliance on price alone and losing it in availability.
- Comparing quotations with different port terms and calling the lower number cheaper.
Review the list with an owner-operator team before the order is placed — they will recognise most of them.
Commissioning checklist
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Measure noise and dust at the operator position against the local limit.
- Measure and log the as-new CSS / setting for future wear comparison.
- Dry-run the plant empty for the specified period and record vibration.
- Test emergency stops, pull wires and interlock trips in sequence.
- Confirm the direction and tension of every belt under no load.
- Sample each product fraction and compare with the specification.
On a brownfield extension, allow extra time for the dust and noise measurements.