Overview
A 200–300 tph crushing plant is a common size for Turkey. Main machines: large jaw + 2× cone + screens. Mid-size quarry, multiple products.

Main equipment
- large jaw + 2× cone + screens
- Shipped to Istanbul.
- Configured to 380V 50Hz / TS EN.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Turkey
- Port: Istanbul.
- Voltage: 380V 50Hz.
- Standards: TS EN.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 200–300 t/h |
| Typical main line | large jaw + 2× cone + screens |
| Scale note | Mid-size quarry, multiple products. |
| Destination port | Istanbul |
| Site supply | 380V 50Hz |
| Local standards | TS EN |
| Region | Europe/Asia |
| Assumed duty | continuous quarry production |
| Evaluation horizon | three-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | three-year view |
| Site condition | a coastal export terminal |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Plan training for a mixed local and expatriate team on CSS adjustment, liner change-out and lock-out / tag-out.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Book container or flat-rack space to Istanbul and prepare the customs document set in advance.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Lay out the large jaw + 2× cone + screens arrangement with straight conveyor runs and crane access for liner changes.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Closed-side setting range and whether automatic setting regulation is included.
- Dust and noise control designed to the local emission limits for Turkey.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
Share this list with a mixed local and expatriate team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Letting the continuous quarry production duty be defined verbally instead of in the contract.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Using one liner profile for both secondary and tertiary stages.
For continuous quarry production, protect the lowest energy per tonne requirement explicitly in the contract documents.
Commissioning checklist
- Confirm the direction and tension of every belt under no load.
- Record power draw, tonnage and chamber pressure at steady state.
- Measure and log the as-new CSS / setting for future wear comparison.
- Confirm all guards, emergency stops and pull-wire switches function.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Check belt tracking, chute build-up and transfer-point dust.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
On a coastal export terminal, allow extra time for the dust and noise measurements.