Overview
A 300–500 tph crushing plant is one of the most requested export sizes. Main machines: primary gyratory/jaw + cone train. Commercial aggregate production.

Main equipment
- primary gyratory/jaw + cone train
- Feeders and multiple screens for 3–4 products.
- Conveyors, control cabinet and (recommended) dust suppression.
How to select
- Base capacity on SALEABLE t/h at required sizes, +10–20% surge.
- Hard rock → jaw + cone; soft rock → jaw + impact.
- Add VSI only when sand / shape is required.
300–500 TPH reference
| Capacity band | Typical main machines | Note |
|---|---|---|
| 300–500 TPH | primary gyratory/jaw + cone train | Commercial aggregate production. |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 300–500 t/h |
| Typical main line | primary gyratory/jaw + cone train |
| Scale note | Commercial aggregate production. |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | five-year view |
At seasonal road-project supply, the ranking of these parameters changes: strict product cubicity usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | strict product cubicity |
| Evaluation horizon | five-year view |
| Site condition | an existing quarry bench |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Review the crusher chamber profile with the liner supplier against the feed material.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Size the primary stage for 300–500 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
Shortening this sequence is possible on an existing quarry bench, but only where the feed and product specification are already fully defined.

What to verify before you sign
- After-sales response time, technician availability and the warranty exclusions in writing.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Availability of a mixed local and expatriate team for liner changes and the lifting equipment on site.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Choke-feed arrangement: surge bin, feeder control and level indication.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Overlooking dust, noise and water permits in your market until erection has already started.
- Using one liner profile for both secondary and tertiary stages.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Skipping a geotechnical check and discovering settlement under the primary crusher at an existing quarry bench.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
Review the list with a mixed local and expatriate team before the order is placed — they will recognise most of them.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure noise and dust at the operator position against the local limit.
- Check belt tracking, chute build-up and transfer-point dust.
- Measure and log the as-new CSS / setting for future wear comparison.
- Record power draw, tonnage and chamber pressure at steady state.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Calibrate the belt scale and any level probes against a known load.
- Sample each product fraction and compare with the specification.
The commissioning record becomes the reference for every liner change in the five-year plan.