Overview
A above 800 tph crushing plant is a common size for Japan. Main machines: gyratory primary + SAG feed. Mine-scale, often with HPGR.

Main equipment
- gyratory primary + SAG feed
- Shipped to Yokohama.
- Configured to 200V 50/60Hz / JIS.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Japan
- Port: Yokohama.
- Voltage: 200V 50/60Hz.
- Standards: JIS.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 800–1500 t/h |
| Typical main line | gyratory primary + SAG feed |
| Scale note | Mine-scale, often with HPGR. |
| Destination port | Yokohama |
| Site supply | 200V 50/60Hz |
| Local standards | JIS |
| Region | Asia |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | five-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | fast mobilisation |
| Evaluation horizon | five-year view |
| Site condition | a remote mine site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Lay out the gyratory primary + SAG feed arrangement with straight conveyor runs and crane access for liner changes.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Book container or flat-rack space to Yokohama and prepare the customs document set in advance.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
On mine pre-beneficiation feed, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.

What to verify before you sign
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for 800–1500 t/h.
- Closed-side setting range and whether automatic setting regulation is included.
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Energy draw in kW and the expected kWh per tonne at the design duty.
For mine pre-beneficiation feed, give the fast mobilisation line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 56% | Model size, number of stages and automation level |
| Ocean freight & insurance | 10% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 13% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 6% | kWh per tonne, local tariff and dust suppression water |
A five-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Undersizing the screen, then blaming the crusher for a plant that never reaches 800–1500 t/h.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Overlooking dust, noise and water permits in Japan until erection has already started.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Dry-run the plant empty for the specified period and record vibration.
- Record the baseline grading curve for each product fraction.
- Confirm all guards, emergency stops and pull-wire switches function.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure and log the as-new CSS / setting for future wear comparison.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Calibrate the belt scale and any level probes against a known load.
The commissioning record becomes the reference for every liner change in the five-year plan.