Overview
A 100–200 tph crushing plant is one of the most requested export sizes. Main machines: PE/PEW jaw + cone + 3-deck screen. Most common export plant size.

Why mobile at this size
- Fast relocation between benches / sites.
- Plug-and-produce, low civil work.
- Diesel-electric or grid power options.
Mobile types
- Wheel-mounted: lower cost, needs a tow.
- Tracked: self-propelled, rough terrain.
- 3-in-1 / 4-in-1: combined crush + screen.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 100–200 t/h |
| Typical main line | PE/PEW jaw + cone + 3-deck screen |
| Scale note | Most common export plant size. |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | three-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | three-year view |
| Site condition | a greenfield site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Lay out the PE/PEW jaw + cone + 3-deck screen arrangement with straight conveyor runs and crane access for liner changes.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Book shipping, prepare the packing list and confirm the container loading plan.
Shortening this sequence is possible on a greenfield site, but only where the feed and product specification are already fully defined.
What to verify before you sign
- Written performance guarantee, sampling method and acceptance-test protocol.
- Liner alloy: Mn22 matched to the rock, not to the lowest purchase price.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Availability of an owner-operator team for liner changes and the lifting equipment on site.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A three-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 100–200 t/h.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
For mine pre-beneficiation feed, protect the maximum mechanical availability requirement explicitly in the contract documents.
Commissioning checklist
- Check belt tracking, chute build-up and transfer-point dust.
- Record power draw, tonnage and chamber pressure at steady state.
- Confirm the direction and tension of every belt under no load.
- Measure and log the as-new CSS / setting for future wear comparison.
- Calibrate the belt scale and any level probes against a known load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Measure noise and dust at the operator position against the local limit.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
For an owner-operator team, run through this list twice — once with the supervisor and once without.