Overview
A under 50 tph crushing plant is one of the most requested export sizes. Main machines: small jaw + impact/cone, skid or mobile. Contractor and pilot scale, fast set-up.

Main equipment
- small jaw + impact/cone, skid or mobile
- Feeders and a screen for 2–3 products.
- Conveyors, control cabinet and (recommended) dust suppression.
How to select
- Base capacity on SALEABLE t/h at required sizes, +10–20% surge.
- Hard rock → jaw + cone; soft rock → jaw + impact.
- Add VSI only when sand / shape is required.
Under 50 TPH reference
| Capacity band | Typical main machines | Note |
|---|---|---|
| Under 50 TPH | small jaw + impact/cone, skid or mobile | Contractor and pilot scale, fast set-up. |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 10–50 t/h |
| Typical main line | small jaw + impact/cone, skid or mobile |
| Scale note | Contractor and pilot scale, fast set-up. |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | seven-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | seven-year view |
| Site condition | a coastal export terminal |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.

What to verify before you sign
- Product sampling points and the lab equipment needed for routine grading checks.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Local service partner, technician travel time and visa requirements for your market.
- Guaranteed power draw and the lowest cost per tonne trade-off it implies.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for 10–50 t/h.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 16% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Using one liner profile for both secondary and tertiary stages.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 10–50 t/h.
Review the list with a rotating shift crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Record the baseline grading curve for each product fraction.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Test emergency stops, pull wires and interlock trips in sequence.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify rotation direction on every motor before coupling.
- Calibrate the belt scale and any level probes against a known load.
- Confirm the direction and tension of every belt under no load.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
The commissioning record becomes the reference for every liner change in the seven-year plan.