Overview
A 100–200 tph crushing plant is one of the most requested export sizes. Main machines: PE/PEW jaw + cone + 3-deck screen. Most common export plant size.

Main equipment
- PE/PEW jaw + cone + 3-deck screen
- Feeders and a screen for 2–3 products.
- Conveyors, control cabinet and (recommended) dust suppression.
How to select
- Base capacity on SALEABLE t/h at required sizes, +10–20% surge.
- Hard rock → jaw + cone; soft rock → jaw + impact.
- Add VSI only when sand / shape is required.
100–200 TPH reference
| Capacity band | Typical main machines | Note |
|---|---|---|
| 100–200 TPH | PE/PEW jaw + cone + 3-deck screen | Most common export plant size. |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 100–200 t/h |
| Typical main line | PE/PEW jaw + cone + 3-deck screen |
| Scale note | Most common export plant size. |
| Assumed duty | continuous quarry production |
| Evaluation horizon | ten-year view |
These values are the starting point for a written proposal on the crushing and screening plant; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | strict product cubicity |
| Evaluation horizon | ten-year view |
| Site condition | a remote mine site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Size the primary stage for 100–200 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Lay out the PE/PEW jaw + cone + 3-deck screen arrangement with straight conveyor runs and crane access for liner changes.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Control system language, telemetry and remote diagnostics availability.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Local service partner, technician travel time and visa requirements for your market.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for 100–200 t/h.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A ten-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Undersizing the screen, then blaming the crusher for a plant that never reaches 100–200 t/h.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Letting the continuous quarry production duty be defined verbally instead of in the contract.
- Using one liner profile for both secondary and tertiary stages.
- Comparing quotations with different port terms and calling the lower number cheaper.
Review the list with a rotating shift crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Calibrate the belt scale and any level probes against a known load.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Test emergency stops, pull wires and interlock trips in sequence.
- Record power draw, tonnage and chamber pressure at steady state.
- Verify rotation direction on every motor before coupling.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Confirm the direction and tension of every belt under no load.
The commissioning record becomes the reference for every liner change in the ten-year plan.