Overview
A 50–100 tph crushing plant is one of the most requested export sizes. Main machines: PE jaw + PF impact / cone + 2-deck screen. Small quarries and concrete plants.

Site requirements
- Level pad ~800–1,500 m².
- Power: standard grid at local voltage.
- Water for dust control (if fitted).
- Stockpile and truck-loading space.
Civil work
Foundations are referenced from the HAMAC general layout; a geotechnical check is recommended for > 300 t/h plants.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 50–100 t/h |
| Typical main line | PE jaw + PF impact / cone + 2-deck screen |
| Scale note | Small quarries and concrete plants. |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | five-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | fast mobilisation |
| Evaluation horizon | five-year view |
| Site condition | a remote mine site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Book shipping, prepare the packing list and confirm the container loading plan.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Lay out the PE jaw + PF impact / cone + 2-deck screen arrangement with straight conveyor runs and crane access for liner changes.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
For a mixed local and expatriate team, the commissioning and training steps need more calendar time than the mechanical erection itself.
What to verify before you sign
- Product sampling points and the lab equipment needed for routine grading checks.
- Availability of a mixed local and expatriate team for liner changes and the lifting equipment on site.
- Wear-part interchangeability across machines in the same circuit.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Control system language, telemetry and remote diagnostics availability.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Closed-side setting range and whether automatic setting regulation is included.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Letting the manufactured-sand production duty be defined verbally instead of in the contract.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
Review the list with a mixed local and expatriate team before the order is placed — they will recognise most of them.
Commissioning checklist
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Confirm the direction and tension of every belt under no load.
- Calibrate the belt scale and any level probes against a known load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure noise and dust at the operator position against the local limit.
- Record power draw, tonnage and chamber pressure at steady state.
- Check belt tracking, chute build-up and transfer-point dust.
The commissioning record becomes the reference for every liner change in the five-year plan.