Overview
Ground to filler / functional grades. HAMAC designs crushing, screening and grinding circuits for industrial minerals & powder across capacities.

Scope
- Calcite (Mohs 3, ~100 MPa)
- Barite (Mohs 3, ~80 MPa)
- Gypsum (Mohs 1.5, ~30 MPa)
- Dolomite (Mohs 3.5, ~110 MPa)
Typical flow
Feed → primary → secondary/tertiary → screening → (VSI / grinding) → stockpile.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Application | Industrial Minerals & Powder |
| Typical feed | Calcite, Barite, Gypsum, Dolomite |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | seven-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and seven-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | seven-year view |
| Site condition | a remote mine site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Review the crusher chamber profile with the liner supplier against the feed material.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.
What to verify before you sign
- Control system language, telemetry and remote diagnostics availability.
- Closed-side setting range and whether automatic setting regulation is included.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Wear-part interchangeability across machines in the same circuit.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Comparing quotations with different port terms and calling the lower number cheaper.
For contract crushing on short-term sites, protect the maximum mechanical availability requirement explicitly in the contract documents.
Commissioning checklist
- Verify rotation direction on every motor before coupling.
- Measure noise and dust at the operator position against the local limit.
- Confirm the direction and tension of every belt under no load.
- Check lubrication levels, grease lines and oil cooler operation.
- Test emergency stops, pull wires and interlock trips in sequence.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Measure and log the as-new CSS / setting for future wear comparison.
For a mixed local and expatriate team, run through this list twice — once with the supervisor and once without.