Overview
Selected HAMAC references relevant to coal & energy:

References
- 100-120tph mobile crushing and screening plant in Algeria
- 100-120tph mobile crushing and screening plant in Chile
- 1500t/d Gold Ore Processing Plant in Tanzania
- 150-180tph stationary crushing and screening plant in Jamaica
- 150tph stationary crushing and screening plant in Iraq
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Coal |
| Mohs hardness | 2 |
| Compressive strength | ~40 MPa |
| Abrasiveness | Low |
| Recommended circuit | impact / jaw with gentle reduction |
| Application | Coal & Energy |
| Typical feed | Coal, Bauxite |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | five-year view |
At demolition and recycling duties, the ranking of these parameters changes: maximum mechanical availability usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | five-year view |
| Site condition | a remote mine site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for coal crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
For an owner-operator team, the commissioning and training steps need more calendar time than the mechanical erection itself.
What to verify before you sign
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Whether the quoted t/h is achieved at demolition and recycling duties or under ideal laboratory feed.
- Dust and noise control designed to the local emission limits for your market.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Local service partner, technician travel time and visa requirements for your market.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Product sampling points and the lab equipment needed for routine grading checks.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
For demolition and recycling duties, give the maximum mechanical availability line extra weight; a generic checklist will not rank the offers correctly.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 55% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 13% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a low-abrasion feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Using one liner profile for both secondary and tertiary stages.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
Review the list with an owner-operator team before the order is placed — they will recognise most of them.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Calibrate the belt scale and any level probes against a known load.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Check lubrication levels, grease lines and oil cooler operation.
- Sample each product fraction and compare with the specification.
- Dry-run the plant empty for the specified period and record vibration.
On a remote mine site, allow extra time for the dust and noise measurements.