Design basis for river pebble asphalt aggregate supply
The design basis starts with the rock, not the machine. River pebble is rated at 100–200 MPa compressive strength with very high abrasiveness, medium moisture sensitivity and a loose bulk density around 1.48 t/m³. Rounded, high-silica feed resists compression and wears blow bars quickly; rock-on-rock VSI is normally preferred for the shaping stage. A change in one stage changes the circulating load in all the others.
A asphalt aggregate supply must produce cubical, low-fines chips for asphalt plants, constrained by a narrow 5–16 mm fraction with low moisture. The commercial priority is particle shape. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 450 mm and target fractions of manufactured sand, 5–20 mm aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | River pebble · 100–200 MPa · abrasion very high |
| Design throughput | 110 t/h saleable product (100–220 t/h scenario band) |
| Maximum feed size | ~450 mm |
| Target product | manufactured sand, 5–20 mm aggregate |
| Loose bulk density | 1.48 t/m³ |
| Suggested circuit | jaw → cone → VSI → sand washer / classifier |

Why tramp metal damage appears in this circuit
A bucket tooth or rebar reaches the chamber and damages liners. In a river pebble asphalt aggregate supply this is usually a system symptom rather than a single machine fault. Start from the product specification and work backwards to the feed.
- no magnet or detector ahead of the crusher
- hydraulic relief and tramp-release settings are untested
- demolition feed is not pre-sorted
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) test the detector with a sample metal piece each week; 2) inspect the chamber after any release event; 3) log every tramp incident and its cause. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For river pebble at 110 t/h the working train is jaw → cone → VSI → sand washer / classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for river pebble and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~138 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~18 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 30% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.48 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 300 kW order-of-magnitude connected load |
The corrective actions for tramp metal damage are applied on top of this base circuit: fit a magnetic separator and a belt metal detector; test hydraulic release under no-load conditions; add a picking station for reinforced concrete feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 30% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Test the detector with a sample metal piece each week
- Inspect the chamber after any release event
- Log every tramp incident and its cause
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 110 t/h nominal |
| Grading | Full sieve analysis, agreed standard, manufactured sand, 5–20 mm aggregate |
| Crusher setting | CSS measured and logged, ~18 mm starting point |
| Power | Main-drive current at steady feed, 300 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for river pebble, while particle shape determines how much lost production actually costs. Start from the product specification and work backwards to the feed.
- Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.