● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Commissioning

Gold ore greenfield plant: Tramp metal damage — solution & design basis

A bucket tooth or rebar reaches the chamber and damages liners — a 250 t/h design basis, configuration and acceptance checks.

Gold ore greenfield plant with tramp metal damage is normally resolved by checking the circuit against the saleable product specification first: fit a magnetic separator and a belt metal detector. For a 250 t/h design point on gold ore, HAMAC would review jaw → cone / impact → screen, then confirm the settings with a written acceptance test. The cheapest fix is usually a settings change; the most expensive is a new machine.

250 t/hindicative design point
60–200 MPacompressive strength
200–400 t/hscenario capacity band
610 kWorder-of-magnitude installed power
Key takeaways
  1. Gold ore is medium in abrasiveness and medium in moisture sensitivity; Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage.
  2. For greenfield plant the priority is a verifiable mass balance, constrained by an untested feed gradation and a fixed commissioning date.
  3. Tramp metal damage typically appears as: a bucket tooth or rebar reaches the chamber and damages liners.
  4. First corrective action: fit a magnetic separator and a belt metal detector.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for gold ore greenfield plant

The design basis starts with the rock, not the machine. Gold ore is rated at 60–200 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.80 t/m³. Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage. Measurements are only comparable when the sieve standard is the same.

A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 250 t/h of saleable product, with a maximum feed top size near 650 mm and target fractions of −10 mm mill feed or heap-leach agglomerate.

Gold ore — design basis (nominal values)
ParameterIndicative value / method
Raw materialGold ore · 60–200 MPa · abrasion medium
Design throughput250 t/h saleable product (200–400 t/h scenario band)
Maximum feed size~650 mm
Target product−10 mm mill feed or heap-leach agglomerate
Loose bulk density1.80 t/m³
Suggested circuitjaw → cone / impact → screen
Gold ore greenfield plant — Design basis for gold ore greenfield plant — HAMAC impact crusher
Gold ore greenfield plant — Design basis for gold ore greenfield plant — HAMAC impact crusher reference.

Why tramp metal damage appears in this circuit

A bucket tooth or rebar reaches the chamber and damages liners. In a gold ore greenfield plant this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.

  • no magnet or detector ahead of the crusher
  • hydraulic relief and tramp-release settings are untested
  • demolition feed is not pre-sorted

The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) test the detector with a sample metal piece each week; 2) inspect the chamber after any release event; 3) log every tramp incident and its cause. Confirm all figures in a written proposal before purchase.

Recommended equipment configuration

For gold ore at 250 t/h the working train is jaw → cone / impact → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gold ore and for a softer rock. Measurements are only comparable when the sieve standard is the same.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~313 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~30 mm at the secondary stage
Secondary / tertiarycone / impact
ScreeningMulti-deck screen sized for 70% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.80 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 610 kW order-of-magnitude connected load

The corrective actions for tramp metal damage are applied on top of this base circuit: fit a magnetic separator and a belt metal detector; test hydraulic release under no-load conditions; add a picking station for reinforced concrete feed.

Gold ore greenfield plant — Recommended equipment configuration — HAMAC impact crusher
Gold ore greenfield plant — Recommended equipment configuration — HAMAC impact crusher reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 70% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.

  • Test the detector with a sample metal piece each week
  • Inspect the chamber after any release event
  • Log every tramp incident and its cause
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 250 t/h nominal
GradingFull sieve analysis, agreed standard, −10 mm mill feed or heap-leach agglomerate
Crusher settingCSS measured and logged, ~30 mm starting point
PowerMain-drive current at steady feed, 610 kW connected load
WearLiner mass before and after, cost per saleable tonne

Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gold ore, while a verifiable mass balance determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.

  • Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 250 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Measurements are only comparable when the sieve standard is the same. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Gold ore greenfield plant — Cost, risk and what to confirm in writing — HAMAC impact crusher
Gold ore greenfield plant — Cost, risk and what to confirm in writing — HAMAC impact crusher reference.
FAQ

Gold ore greenfield plant — questions answered

Direct answers to the questions buyers ask most often.

What causes tramp metal damage in a gold ore greenfield plant?

A bucket tooth or rebar reaches the chamber and damages liners. The usual causes are no magnet or detector ahead of the crusher; hydraulic relief and tramp-release settings are untested; demolition feed is not pre-sorted. fit a magnetic separator and a belt metal detector.

Which crusher train suits gold ore at 200–400 t/h?

A typical configuration is jaw → cone / impact → screen. Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 250 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call