Design basis for river pebble manufactured sand production
The design basis starts with the rock, not the machine. River pebble is rated at 100–200 MPa compressive strength with very high abrasiveness, medium moisture sensitivity and a loose bulk density around 1.48 t/m³. Rounded, high-silica feed resists compression and wears blow bars quickly; rock-on-rock VSI is normally preferred for the shaping stage. Operator notes from the first month are often the best diagnostic data.
A manufactured sand production must control the 0–4 mm fraction and its fines content, constrained by varying feed moisture and a limited water supply. The commercial priority is fines control. For this combination HAMAC works from an indicative design point of 120 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of manufactured sand, 5–20 mm aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | River pebble · 100–200 MPa · abrasion very high |
| Design throughput | 120 t/h saleable product (80–200 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | manufactured sand, 5–20 mm aggregate |
| Loose bulk density | 1.48 t/m³ |
| Suggested circuit | jaw → cone → VSI → sand washer / classifier |

Why restricted site footprint appears in this circuit
The required circuit will not fit the available bench or yard. In a river pebble manufactured sand production this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- conveyor inclines and transfer towers consume most of the area
- stockpile and maintenance access were not included in the layout
- the flow sheet assumes a straight-line arrangement
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) draw the layout to scale with conveyor inclines; 2) check crusher removal clearance; 3) verify truck turning radius and stockpile reach. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For river pebble at 120 t/h the working train is jaw → cone → VSI → sand washer / classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for river pebble and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~150 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~22 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 60% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.48 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 260 kW order-of-magnitude connected load |
The corrective actions for restricted site footprint are applied on top of this base circuit: fold the circuit with a compact elevator or modular tower; place the screen above the crusher in a closed loop; reserve a maintenance lane for liner change-outs.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 22 mm, a circulating load around 60% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Draw the layout to scale with conveyor inclines
- Check crusher removal clearance
- Verify truck turning radius and stockpile reach
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 120 t/h nominal |
| Grading | Full sieve analysis, agreed standard, manufactured sand, 5–20 mm aggregate |
| Crusher setting | CSS measured and logged, ~22 mm starting point |
| Power | Main-drive current at steady feed, 260 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for river pebble, while fines control determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 60% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 120 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.