Design basis for iron ore wet tropical climate
The design basis starts with the rock, not the machine. Iron ore is rated at 80–250 MPa compressive strength with medium–high abrasiveness, medium moisture sensitivity and a loose bulk density around 2.10 t/m³. High bulk density means belts and bins must be sized by mass, while moisture drives screen blinding in the fines circuit. The reference conditions should be attached to every figure quoted.
A wet tropical climate must keep screening reliable through a long rainy season, constrained by high feed moisture and clay-bearing overburden. The commercial priority is wet screening and washing. For this combination HAMAC works from an indicative design point of 120 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of −10 mm fines and sized lump ore.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Iron ore · 80–250 MPa · abrasion medium–high |
| Design throughput | 120 t/h saleable product (120–300 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | −10 mm fines and sized lump ore |
| Loose bulk density | 2.10 t/m³ |
| Suggested circuit | jaw / gyratory → cone → screen → magnetic separation |

Why start-up instability appears in this circuit
The plant cannot hold a steady feed during its first weeks. In a iron ore wet tropical climate this is usually a system symptom rather than a single machine fault. Two plants with the same nominal t/h can have very different operating costs.
- interlocks and feeder ramp rates were never tuned together
- settings were changed without a commissioning log
- operators were trained on a different circuit
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For iron ore at 120 t/h the working train is jaw / gyratory → cone → screen → magnetic separation. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for iron ore and for a softer rock. The reference conditions should be attached to every figure quoted.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~150 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~18 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 2.10 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 350 kW order-of-magnitude connected load |
The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 20% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Verify every interlock in no-load and loaded runs
- Sign off the settings log with both parties
- Repeat a full sieve analysis after the first 100 hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 120 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −10 mm fines and sized lump ore |
| Crusher setting | CSS measured and logged, ~18 mm starting point |
| Power | Main-drive current at steady feed, 350 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for iron ore, while wet screening and washing determines how much lost production actually costs. Two plants with the same nominal t/h can have very different operating costs.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 120 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
The reference conditions should be attached to every figure quoted. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.