Design basis for iron ore greenfield plant
The design basis starts with the rock, not the machine. Iron ore is rated at 80–250 MPa compressive strength with medium–high abrasiveness, medium moisture sensitivity and a loose bulk density around 2.10 t/m³. High bulk density means belts and bins must be sized by mass, while moisture drives screen blinding in the fines circuit. Operator notes from the first month are often the best diagnostic data.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 250 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of −10 mm fines and sized lump ore.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Iron ore · 80–250 MPa · abrasion medium–high |
| Design throughput | 250 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | −10 mm fines and sized lump ore |
| Loose bulk density | 2.10 t/m³ |
| Suggested circuit | jaw / gyratory → cone → screen → magnetic separation |

Why off-specification grading appears in this circuit
The product sieve curve drifts outside its envelope between shifts. In a iron ore greenfield plant this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- CSS has moved as liners wear and was not re-measured
- screen media is worn, blinded or stretched
- feed gradation changes as the quarry face advances
A change in one stage changes the circulating load in all the others. Before changing a crusher setting, check these in order: 1) run a full sieve analysis on each product fraction; 2) compare current CSS with the commissioning log; 3) inspect every deck for torn or blinded panels. HAMAC states nominal values alongside the conditions they were measured under.
Recommended equipment configuration
For iron ore at 250 t/h the working train is jaw / gyratory → cone → screen → magnetic separation. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for iron ore and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~313 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 2.10 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 550 kW order-of-magnitude connected load |
The corrective actions for off-specification grading are applied on top of this base circuit: measure and log css after every liner change; set a screen-panel replacement interval based on aperture wear; adjust the closed-circuit return rate before changing the crusher setting.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 70% and a screen efficiency target above 90%. A change in one stage changes the circulating load in all the others.
- Run a full sieve analysis on each product fraction
- Compare current CSS with the commissioning log
- Inspect every deck for torn or blinded panels
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 250 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −10 mm fines and sized lump ore |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 550 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
HAMAC states nominal values alongside the conditions they were measured under. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for iron ore, while a verifiable mass balance determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 250 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. HAMAC states nominal values alongside the conditions they were measured under. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.