Design basis for quartzite railway ballast production
The design basis starts with the rock, not the machine. Quartzite is rated at 150–300 MPa compressive strength with very high abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Extreme silica content makes liner consumption the dominant operating cost; impact stages are avoided wherever the specification allows. Record the setting before adjusting it, or the baseline is lost.
A railway ballast production must maximise the 25–50 mm fraction with minimal waste, constrained by strict flakiness and abrasion specifications. The commercial priority is yield of the saleable fraction. For this combination HAMAC works from an indicative design point of 180 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of high-specification aggregate and industrial sand.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Quartzite · 150–300 MPa · abrasion very high |
| Design throughput | 180 t/h saleable product (150–350 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | high-specification aggregate and industrial sand |
| Loose bulk density | 1.52 t/m³ |
| Suggested circuit | jaw → cone → cone → screen |

Why start-up instability appears in this circuit
The plant cannot hold a steady feed during its first weeks. In a quartzite railway ballast production this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.
- interlocks and feeder ramp rates were never tuned together
- settings were changed without a commissioning log
- operators were trained on a different circuit
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. HAMAC states nominal values alongside the conditions they were measured under.
Recommended equipment configuration
For quartzite at 180 t/h the working train is jaw → cone → cone → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for quartzite and for a softer rock. Record the setting before adjusting it, or the baseline is lost.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~225 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~26 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 50% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.52 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 400 kW order-of-magnitude connected load |
The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 26 mm, a circulating load around 50% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Verify every interlock in no-load and loaded runs
- Sign off the settings log with both parties
- Repeat a full sieve analysis after the first 100 hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 180 t/h nominal |
| Grading | Full sieve analysis, agreed standard, high-specification aggregate and industrial sand |
| Crusher setting | CSS measured and logged, ~26 mm starting point |
| Power | Main-drive current at steady feed, 400 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
HAMAC states nominal values alongside the conditions they were measured under. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for quartzite, while yield of the saleable fraction determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.
- Ask every supplier for the same flow sheet and mass balance, including the 50% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 180 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Record the setting before adjusting it, or the baseline is lost. HAMAC states nominal values alongside the conditions they were measured under. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.