Design basis for dolomite contract crushing
The design basis starts with the rock, not the machine. Dolomite is rated at 60–180 MPa compressive strength with low–medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.42 t/m³. Suits impact crushing and downstream grinding; the fines fraction is often the most valuable product. Indicative values are starting points for a design, not guarantees.
A contract crushing must relocate between sites with minimal erection time, constrained by short project duration and no permanent foundations. The commercial priority is mobility and fast set-up. For this combination HAMAC works from an indicative design point of 120 t/h of saleable product, with a maximum feed top size near 400 mm and target fractions of aggregate, agricultural lime, filler powder.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Dolomite · 60–180 MPa · abrasion low–medium |
| Design throughput | 120 t/h saleable product (80–200 t/h scenario band) |
| Maximum feed size | ~400 mm |
| Target product | aggregate, agricultural lime, filler powder |
| Loose bulk density | 1.42 t/m³ |
| Suggested circuit | impact crusher → screen → optional Raymond mill |

Why restricted site footprint appears in this circuit
The required circuit will not fit the available bench or yard. In a dolomite contract crushing this is usually a system symptom rather than a single machine fault. Most of these problems are diagnosed at the screen, not at the crusher.
- conveyor inclines and transfer towers consume most of the area
- stockpile and maintenance access were not included in the layout
- the flow sheet assumes a straight-line arrangement
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) draw the layout to scale with conveyor inclines; 2) check crusher removal clearance; 3) verify truck turning radius and stockpile reach. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For dolomite at 120 t/h the working train is impact crusher → screen → optional Raymond mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for dolomite and for a softer rock. Indicative values are starting points for a design, not guarantees.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~150 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~18 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 60% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.42 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 380 kW order-of-magnitude connected load |
The corrective actions for restricted site footprint are applied on top of this base circuit: fold the circuit with a compact elevator or modular tower; place the screen above the crusher in a closed loop; reserve a maintenance lane for liner change-outs.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 60% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Draw the layout to scale with conveyor inclines
- Check crusher removal clearance
- Verify truck turning radius and stockpile reach
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 120 t/h nominal |
| Grading | Full sieve analysis, agreed standard, aggregate, agricultural lime, filler powder |
| Crusher setting | CSS measured and logged, ~18 mm starting point |
| Power | Main-drive current at steady feed, 380 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for dolomite, while mobility and fast set-up determines how much lost production actually costs. Most of these problems are diagnosed at the screen, not at the crusher.
- Ask every supplier for the same flow sheet and mass balance, including the 60% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 120 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Indicative values are starting points for a design, not guarantees. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.