Granite remote site: Off-specification grading — solution & design basis

The product sieve curve drifts outside its envelope between shifts — a 70 t/h design basis, configuration and acceptance checks.

Granite remote site with off-specification grading is normally resolved by checking the circuit against the saleable product specification first: measure and log CSS after every liner change. For a 70 t/h design point on granite, HAMAC would review jaw → cone → cone / VSI → 3-deck screen, then confirm the settings with a written acceptance test. A supplier can only guarantee a figure when the test conditions are written down.

70 t/hindicative design point
100–250 MPacompressive strength
60–180 t/hscenario capacity band
190 kWorder-of-magnitude installed power
Key takeaways
  1. Granite is medium–high in abrasiveness and low in moisture sensitivity; High compressive strength makes compression crushing the economic choice; an impact or VSI stage is added only when cubicity is specified.
  2. For remote site the priority is energy and spares autonomy, constrained by diesel generation and infrequent service visits.
  3. Off-specification grading typically appears as: the product sieve curve drifts outside its envelope between shifts.
  4. First corrective action: measure and log CSS after every liner change.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for granite remote site

The design basis starts with the rock, not the machine. Granite is rated at 100–250 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.45 t/m³. High compressive strength makes compression crushing the economic choice; an impact or VSI stage is added only when cubicity is specified. Indicative values are starting points for a design, not guarantees.

A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 70 t/h of saleable product, with a maximum feed top size near 650 mm and target fractions of 0–5, 5–10, 10–20, 20–40 mm.

Granite — design basis (nominal values)
ParameterIndicative value / method
Raw materialGranite · 100–250 MPa · abrasion medium–high
Design throughput70 t/h saleable product (60–180 t/h scenario band)
Maximum feed size~650 mm
Target product0–5, 5–10, 10–20, 20–40 mm
Loose bulk density1.45 t/m³
Suggested circuitjaw → cone → cone / VSI → 3-deck screen
Granite remote site — Design basis for granite remote site — HAMAC vibrating screen
Granite remote site — Design basis for granite remote site — HAMAC vibrating screen reference.

Why off-specification grading appears in this circuit

The product sieve curve drifts outside its envelope between shifts. In a granite remote site this is usually a system symptom rather than a single machine fault. A supplier can only guarantee a figure when the test conditions are written down.

  • CSS has moved as liners wear and was not re-measured
  • screen media is worn, blinded or stretched
  • feed gradation changes as the quarry face advances

Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) run a full sieve analysis on each product fraction; 2) compare current CSS with the commissioning log; 3) inspect every deck for torn or blinded panels. A signed settings log at handover protects both parties later.

Recommended equipment configuration

For granite at 70 t/h the working train is jaw → cone → cone / VSI → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for granite and for a softer rock. Indicative values are starting points for a design, not guarantees.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~88 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~38 mm at the secondary stage
Secondary / tertiarycone
ScreeningMulti-deck screen sized for 30% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.45 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 190 kW order-of-magnitude connected load

The corrective actions for off-specification grading are applied on top of this base circuit: measure and log css after every liner change; set a screen-panel replacement interval based on aperture wear; adjust the closed-circuit return rate before changing the crusher setting.

Granite remote site — Recommended equipment configuration — HAMAC vibrating screen
Granite remote site — Recommended equipment configuration — HAMAC vibrating screen reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 30% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.

  • Run a full sieve analysis on each product fraction
  • Compare current CSS with the commissioning log
  • Inspect every deck for torn or blinded panels
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 70 t/h nominal
GradingFull sieve analysis, agreed standard, 0–5, 5–10, 10–20, 20–40 mm
Crusher settingCSS measured and logged, ~38 mm starting point
PowerMain-drive current at steady feed, 190 kW connected load
WearLiner mass before and after, cost per saleable tonne

A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for granite, while energy and spares autonomy determines how much lost production actually costs. A supplier can only guarantee a figure when the test conditions are written down.

  • Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 70 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Indicative values are starting points for a design, not guarantees. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Granite remote site — Cost, risk and what to confirm in writing — HAMAC vibrating screen
Granite remote site — Cost, risk and what to confirm in writing — HAMAC vibrating screen reference.
FAQ

Granite remote site — questions answered

Direct answers to the questions buyers ask most often.

What causes off-specification grading in a granite remote site?

The product sieve curve drifts outside its envelope between shifts. The usual causes are css has moved as liners wear and was not re-measured; screen media is worn, blinded or stretched; feed gradation changes as the quarry face advances. measure and log CSS after every liner change.

Which crusher train suits granite at 60–180 t/h?

A typical configuration is jaw → cone → cone / VSI → 3-deck screen. High compressive strength makes compression crushing the economic choice; an impact or VSI stage is added only when cubicity is specified. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 70 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call