● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Mobile plants

Gabbro remote site: Long relocation and set-up time — solution & design basis

The plant loses more days to moving and erection than the contract allows — a 110 t/h design basis, configuration and acceptance checks.

Gabbro remote site with long relocation and set-up time is normally resolved by checking the circuit against the saleable product specification first: standardise plug-in connections and conveyor interfaces. For a 110 t/h design point on gabbro, HAMAC would review jaw → cone → cone → 3-deck screen, then confirm the settings with a written acceptance test. Two plants with the same nominal t/h can have very different operating costs.

110 t/hindicative design point
150–280 MPacompressive strength
60–180 t/hscenario capacity band
350 kWorder-of-magnitude installed power
Key takeaways
  1. Gabbro is medium in abrasiveness and low in moisture sensitivity; Dense and tough, so installed power and conveyor sizing deserve a larger margin than a t/h comparison suggests.
  2. For remote site the priority is energy and spares autonomy, constrained by diesel generation and infrequent service visits.
  3. Long relocation and set-up time typically appears as: the plant loses more days to moving and erection than the contract allows.
  4. First corrective action: standardise plug-in connections and conveyor interfaces.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for gabbro remote site

The design basis starts with the rock, not the machine. Gabbro is rated at 150–280 MPa compressive strength with medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Dense and tough, so installed power and conveyor sizing deserve a larger margin than a t/h comparison suggests. Record the setting before adjusting it, or the baseline is lost.

A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of railway ballast and concrete aggregate.

Gabbro — design basis (nominal values)
ParameterIndicative value / method
Raw materialGabbro · 150–280 MPa · abrasion medium
Design throughput110 t/h saleable product (60–180 t/h scenario band)
Maximum feed size~350 mm
Target productrailway ballast and concrete aggregate
Loose bulk density1.52 t/m³
Suggested circuitjaw → cone → cone → 3-deck screen
Gabbro remote site — Design basis for gabbro remote site — HAMAC mobile crushing plant
Gabbro remote site — Design basis for gabbro remote site — HAMAC mobile crushing plant reference.

Why long relocation and set-up time appears in this circuit

The plant loses more days to moving and erection than the contract allows. In a gabbro remote site this is usually a system symptom rather than a single machine fault. Two plants with the same nominal t/h can have very different operating costs.

  • electrical and conveyor connections differ between modules
  • transport permits and axle loads were checked too late
  • no written set-up sequence exists for the crew

Indicative values are starting points for a design, not guarantees. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) count lifting operations and crane hours; 3) record every connection that needs a tool on site. Ask for the mass balance and the test method behind any quoted number.

Recommended equipment configuration

For gabbro at 110 t/h the working train is jaw → cone → cone → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gabbro and for a softer rock. Record the setting before adjusting it, or the baseline is lost.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~138 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~34 mm at the secondary stage
Secondary / tertiarycone
ScreeningMulti-deck screen sized for 70% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.52 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 350 kW order-of-magnitude connected load

The corrective actions for long relocation and set-up time are applied on top of this base circuit: standardise plug-in connections and conveyor interfaces; verify transport width, height and axle loads before dispatch; write and rehearse a step-by-step set-up checklist.

Gabbro remote site — Recommended equipment configuration — HAMAC mobile crushing plant
Gabbro remote site — Recommended equipment configuration — HAMAC mobile crushing plant reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 34 mm, a circulating load around 70% and a screen efficiency target above 90%. Indicative values are starting points for a design, not guarantees.

  • Time a full move from stop to first feed
  • Count lifting operations and crane hours
  • Record every connection that needs a tool on site
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 110 t/h nominal
GradingFull sieve analysis, agreed standard, railway ballast and concrete aggregate
Crusher settingCSS measured and logged, ~34 mm starting point
PowerMain-drive current at steady feed, 350 kW connected load
WearLiner mass before and after, cost per saleable tonne

Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gabbro, while energy and spares autonomy determines how much lost production actually costs. Two plants with the same nominal t/h can have very different operating costs.

  • Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Record the setting before adjusting it, or the baseline is lost. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Gabbro remote site — Cost, risk and what to confirm in writing — HAMAC mobile crushing plant
Gabbro remote site — Cost, risk and what to confirm in writing — HAMAC mobile crushing plant reference.
FAQ

Gabbro remote site — questions answered

Direct answers to the questions buyers ask most often.

What causes long relocation and set-up time in a gabbro remote site?

The plant loses more days to moving and erection than the contract allows. The usual causes are electrical and conveyor connections differ between modules; transport permits and axle loads were checked too late; no written set-up sequence exists for the crew. standardise plug-in connections and conveyor interfaces.

Which crusher train suits gabbro at 60–180 t/h?

A typical configuration is jaw → cone → cone → 3-deck screen. Dense and tough, so installed power and conveyor sizing deserve a larger margin than a t/h comparison suggests. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 110 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call