Design basis for gabbro remote site
The design basis starts with the rock, not the machine. Gabbro is rated at 150–280 MPa compressive strength with medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Dense and tough, so installed power and conveyor sizing deserve a larger margin than a t/h comparison suggests. Record the setting before adjusting it, or the baseline is lost.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of railway ballast and concrete aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gabbro · 150–280 MPa · abrasion medium |
| Design throughput | 110 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | railway ballast and concrete aggregate |
| Loose bulk density | 1.52 t/m³ |
| Suggested circuit | jaw → cone → cone → 3-deck screen |

Why long relocation and set-up time appears in this circuit
The plant loses more days to moving and erection than the contract allows. In a gabbro remote site this is usually a system symptom rather than a single machine fault. Two plants with the same nominal t/h can have very different operating costs.
- electrical and conveyor connections differ between modules
- transport permits and axle loads were checked too late
- no written set-up sequence exists for the crew
Indicative values are starting points for a design, not guarantees. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) count lifting operations and crane hours; 3) record every connection that needs a tool on site. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For gabbro at 110 t/h the working train is jaw → cone → cone → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gabbro and for a softer rock. Record the setting before adjusting it, or the baseline is lost.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~138 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~34 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.52 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 350 kW order-of-magnitude connected load |
The corrective actions for long relocation and set-up time are applied on top of this base circuit: standardise plug-in connections and conveyor interfaces; verify transport width, height and axle loads before dispatch; write and rehearse a step-by-step set-up checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 34 mm, a circulating load around 70% and a screen efficiency target above 90%. Indicative values are starting points for a design, not guarantees.
- Time a full move from stop to first feed
- Count lifting operations and crane hours
- Record every connection that needs a tool on site
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 110 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast and concrete aggregate |
| Crusher setting | CSS measured and logged, ~34 mm starting point |
| Power | Main-drive current at steady feed, 350 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gabbro, while energy and spares autonomy determines how much lost production actually costs. Two plants with the same nominal t/h can have very different operating costs.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Record the setting before adjusting it, or the baseline is lost. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.