Design basis for iron ore remote site
The design basis starts with the rock, not the machine. Iron ore is rated at 80–250 MPa compressive strength with medium–high abrasiveness, medium moisture sensitivity and a loose bulk density around 2.10 t/m³. High bulk density means belts and bins must be sized by mass, while moisture drives screen blinding in the fines circuit. Record the setting before adjusting it, or the baseline is lost.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 80 t/h of saleable product, with a maximum feed top size near 400 mm and target fractions of −10 mm fines and sized lump ore.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Iron ore · 80–250 MPa · abrasion medium–high |
| Design throughput | 80 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~400 mm |
| Target product | −10 mm fines and sized lump ore |
| Loose bulk density | 2.10 t/m³ |
| Suggested circuit | jaw / gyratory → cone → screen → magnetic separation |

Why restricted site footprint appears in this circuit
The required circuit will not fit the available bench or yard. In a iron ore remote site this is usually a system symptom rather than a single machine fault. A supplier can only guarantee a figure when the test conditions are written down.
- conveyor inclines and transfer towers consume most of the area
- stockpile and maintenance access were not included in the layout
- the flow sheet assumes a straight-line arrangement
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) draw the layout to scale with conveyor inclines; 2) check crusher removal clearance; 3) verify truck turning radius and stockpile reach. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For iron ore at 80 t/h the working train is jaw / gyratory → cone → screen → magnetic separation. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for iron ore and for a softer rock. Record the setting before adjusting it, or the baseline is lost.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~100 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~22 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 2.10 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 200 kW order-of-magnitude connected load |
The corrective actions for restricted site footprint are applied on top of this base circuit: fold the circuit with a compact elevator or modular tower; place the screen above the crusher in a closed loop; reserve a maintenance lane for liner change-outs.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 22 mm, a circulating load around 40% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Draw the layout to scale with conveyor inclines
- Check crusher removal clearance
- Verify truck turning radius and stockpile reach
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 80 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −10 mm fines and sized lump ore |
| Crusher setting | CSS measured and logged, ~22 mm starting point |
| Power | Main-drive current at steady feed, 200 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for iron ore, while energy and spares autonomy determines how much lost production actually costs. A supplier can only guarantee a figure when the test conditions are written down.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 80 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Record the setting before adjusting it, or the baseline is lost. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.