Design basis for granite arid desert site
The design basis starts with the rock, not the machine. Granite is rated at 100–250 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.45 t/m³. High compressive strength makes compression crushing the economic choice; an impact or VSI stage is added only when cubicity is specified. Indicative values are starting points for a design, not guarantees.
A arid desert site must control dust with very little water available, constrained by extreme heat, abrasive airborne dust and limited water. The commercial priority is dry dust extraction. For this combination HAMAC works from an indicative design point of 170 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of 0–5, 5–10, 10–20, 20–40 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Granite · 100–250 MPa · abrasion medium–high |
| Design throughput | 170 t/h saleable product (150–350 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | 0–5, 5–10, 10–20, 20–40 mm |
| Loose bulk density | 1.45 t/m³ |
| Suggested circuit | jaw → cone → cone / VSI → 3-deck screen |

Why tramp metal damage appears in this circuit
A bucket tooth or rebar reaches the chamber and damages liners. In a granite arid desert site this is usually a system symptom rather than a single machine fault. A supplier can only guarantee a figure when the test conditions are written down.
- no magnet or detector ahead of the crusher
- hydraulic relief and tramp-release settings are untested
- demolition feed is not pre-sorted
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) test the detector with a sample metal piece each week; 2) inspect the chamber after any release event; 3) log every tramp incident and its cause. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For granite at 170 t/h the working train is jaw → cone → cone / VSI → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for granite and for a softer rock. Indicative values are starting points for a design, not guarantees.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~213 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~26 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.45 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 500 kW order-of-magnitude connected load |
The corrective actions for tramp metal damage are applied on top of this base circuit: fit a magnetic separator and a belt metal detector; test hydraulic release under no-load conditions; add a picking station for reinforced concrete feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 26 mm, a circulating load around 40% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Test the detector with a sample metal piece each week
- Inspect the chamber after any release event
- Log every tramp incident and its cause
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 170 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–5, 5–10, 10–20, 20–40 mm |
| Crusher setting | CSS measured and logged, ~26 mm starting point |
| Power | Main-drive current at steady feed, 500 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for granite, while dry dust extraction determines how much lost production actually costs. A supplier can only guarantee a figure when the test conditions are written down.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 170 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Indicative values are starting points for a design, not guarantees. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.