Design basis for calcite remote site
The design basis starts with the rock, not the machine. Calcite is rated at 30–90 MPa compressive strength with very low abrasiveness, low moisture sensitivity and a loose bulk density around 1.35 t/m³. Whiteness and D97 control drive the circuit; contamination control and classifier stability are the priority. A change in one stage changes the circulating load in all the others.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 60 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of 200–2500 mesh GCC filler.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Calcite · 30–90 MPa · abrasion very low |
| Design throughput | 60 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | 200–2500 mesh GCC filler |
| Loose bulk density | 1.35 t/m³ |
| Suggested circuit | jaw → impact → Raymond / ball mill + classifier |

Why start-up instability appears in this circuit
The plant cannot hold a steady feed during its first weeks. In a calcite remote site this is usually a system symptom rather than a single machine fault. A supplier can only guarantee a figure when the test conditions are written down.
- interlocks and feeder ramp rates were never tuned together
- settings were changed without a commissioning log
- operators were trained on a different circuit
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For calcite at 60 t/h the working train is jaw → impact → Raymond / ball mill + classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for calcite and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~75 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | impact |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.35 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 160 kW order-of-magnitude connected load |
The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 20% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Verify every interlock in no-load and loaded runs
- Sign off the settings log with both parties
- Repeat a full sieve analysis after the first 100 hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 60 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 200–2500 mesh GCC filler |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 160 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for calcite, while energy and spares autonomy determines how much lost production actually costs. A supplier can only guarantee a figure when the test conditions are written down.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 60 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.