Design basis for copper ore underground mine
The design basis starts with the rock, not the machine. Copper ore is rated at 80–220 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.90 t/m³. Product top size is set by the downstream mill, so a closed crushing circuit with tight screen control protects grinding energy. Operator notes from the first month are often the best diagnostic data.
A underground mine must fit crushing equipment into a confined excavation, constrained by restricted headroom, ventilation and haulage access. The commercial priority is compact footprint. For this combination HAMAC works from an indicative design point of 120 t/h of saleable product, with a maximum feed top size near 500 mm and target fractions of −12 mm mill feed.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Copper ore · 80–220 MPa · abrasion medium |
| Design throughput | 120 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~500 mm |
| Target product | −12 mm mill feed |
| Loose bulk density | 1.90 t/m³ |
| Suggested circuit | jaw → cone → screen → grinding circuit |

Why high energy cost per tonne appears in this circuit
KWh per saleable tonne rises while crusher output stays flat. In a copper ore underground mine this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.
- idling and recirculating material are counted as production
- a grinding circuit is oversized for the required fineness
- drives run at fixed speed regardless of feed rate
Indicative values are starting points for a design, not guarantees. Before changing a crusher setting, check these in order: 1) install sub-metering on the main drives; 2) calculate specific energy weekly; 3) compare idle time against loaded running hours. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For copper ore at 120 t/h the working train is jaw → cone → screen → grinding circuit. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for copper ore and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~150 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~34 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.90 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 380 kW order-of-magnitude connected load |
The corrective actions for high energy cost per tonne are applied on top of this base circuit: meter energy against saleable tonnes, not crusher feed; match mill and classifier size to the real d97 target; add vfds to feeders and fans and interlock them with feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 34 mm, a circulating load around 40% and a screen efficiency target above 90%. Indicative values are starting points for a design, not guarantees.
- Install sub-metering on the main drives
- Calculate specific energy weekly
- Compare idle time against loaded running hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 120 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −12 mm mill feed |
| Crusher setting | CSS measured and logged, ~34 mm starting point |
| Power | Main-drive current at steady feed, 380 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for copper ore, while compact footprint determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 120 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.
