● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Economics

Coal greenfield plant: CAPEX justification — solution & design basis

The investment case compares purchase prices instead of lifetime cost — a 250 t/h design basis, configuration and acceptance checks.

Coal greenfield plant with CAPEX justification is normally resolved by checking the circuit against the saleable product specification first: normalise every quote to one written flow sheet. For a 250 t/h design point on coal, HAMAC would review sizer / impact → screen, then confirm the settings with a written acceptance test. The cheapest fix is usually a settings change; the most expensive is a new machine.

250 t/hindicative design point
10–50 MPacompressive strength
200–400 t/hscenario capacity band
800 kWorder-of-magnitude installed power
Key takeaways
  1. Coal is very low in abrasiveness and variable in moisture sensitivity; Low bulk density flips the usual sizing logic: volume, dust and explosion protection dominate over crusher power.
  2. For greenfield plant the priority is a verifiable mass balance, constrained by an untested feed gradation and a fixed commissioning date.
  3. CAPEX justification typically appears as: the investment case compares purchase prices instead of lifetime cost.
  4. First corrective action: normalise every quote to one written flow sheet.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for coal greenfield plant

The design basis starts with the rock, not the machine. Coal is rated at 10–50 MPa compressive strength with very low abrasiveness, variable moisture sensitivity and a loose bulk density around 0.85 t/m³. Low bulk density flips the usual sizing logic: volume, dust and explosion protection dominate over crusher power. Measurements are only comparable when the sieve standard is the same.

A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 250 t/h of saleable product, with a maximum feed top size near 450 mm and target fractions of −50 mm and washed size fractions.

Coal — design basis (nominal values)
ParameterIndicative value / method
Raw materialCoal · 10–50 MPa · abrasion very low
Design throughput250 t/h saleable product (200–400 t/h scenario band)
Maximum feed size~450 mm
Target product−50 mm and washed size fractions
Loose bulk density0.85 t/m³
Suggested circuitsizer / impact → screen
Coal greenfield plant — Design basis for coal greenfield plant — HAMAC crushing and screening equipment
Coal greenfield plant — Design basis for coal greenfield plant — HAMAC crushing and screening equipment reference.

Why CAPEX justification appears in this circuit

The investment case compares purchase prices instead of lifetime cost. In a coal greenfield plant this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.

  • quotes assume different flow sheets and mass balances
  • freight, civils, erection and spares are excluded
  • availability is assumed at 100% in the payback model

The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) request a mass balance with each quotation; 2) confirm the Incoterm and named port; 3) sensitivity-test the payback at 75% utilisation. Confirm all figures in a written proposal before purchase.

Recommended equipment configuration

For coal at 250 t/h the working train is sizer / impact → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for coal and for a softer rock. Measurements are only comparable when the sieve standard is the same.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~313 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~38 mm at the secondary stage
Secondary / tertiaryscreen
ScreeningMulti-deck screen sized for 70% circulating load
ConveyingBelts sized for fresh feed + return stream, 0.85 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 800 kW order-of-magnitude connected load

The corrective actions for CAPEX justification are applied on top of this base circuit: normalise every quote to one written flow sheet; include incoterms, civils, erection and a two-year spares package; model annual tonnage as nameplate × hours × realistic utilisation.

Coal greenfield plant — Recommended equipment configuration — HAMAC crushing and screening equipment
Coal greenfield plant — Recommended equipment configuration — HAMAC crushing and screening equipment reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 70% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.

  • Request a mass balance with each quotation
  • Confirm the Incoterm and named port
  • Sensitivity-test the payback at 75% utilisation
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 250 t/h nominal
GradingFull sieve analysis, agreed standard, −50 mm and washed size fractions
Crusher settingCSS measured and logged, ~38 mm starting point
PowerMain-drive current at steady feed, 800 kW connected load
WearLiner mass before and after, cost per saleable tonne

Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for coal, while a verifiable mass balance determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.

  • Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 250 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Measurements are only comparable when the sieve standard is the same. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Coal greenfield plant — Cost, risk and what to confirm in writing — HAMAC crushing and screening equipment
Coal greenfield plant — Cost, risk and what to confirm in writing — HAMAC crushing and screening equipment reference.
FAQ

Coal greenfield plant — questions answered

Direct answers to the questions buyers ask most often.

What causes CAPEX justification in a coal greenfield plant?

The investment case compares purchase prices instead of lifetime cost. The usual causes are quotes assume different flow sheets and mass balances; freight, civils, erection and spares are excluded; availability is assumed at 100% in the payback model. normalise every quote to one written flow sheet.

Which crusher train suits coal at 200–400 t/h?

A typical configuration is sizer / impact → screen. Low bulk density flips the usual sizing logic: volume, dust and explosion protection dominate over crusher power. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 250 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call