Design basis for granite greenfield plant
The design basis starts with the rock, not the machine. Granite is rated at 100–250 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.45 t/m³. High compressive strength makes compression crushing the economic choice; an impact or VSI stage is added only when cubicity is specified. Measurements are only comparable when the sieve standard is the same.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 200 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of 0–5, 5–10, 10–20, 20–40 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Granite · 100–250 MPa · abrasion medium–high |
| Design throughput | 200 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | 0–5, 5–10, 10–20, 20–40 mm |
| Loose bulk density | 1.45 t/m³ |
| Suggested circuit | jaw → cone → cone / VSI → 3-deck screen |

Why high energy cost per tonne appears in this circuit
KWh per saleable tonne rises while crusher output stays flat. In a granite greenfield plant this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- idling and recirculating material are counted as production
- a grinding circuit is oversized for the required fineness
- drives run at fixed speed regardless of feed rate
A change in one stage changes the circulating load in all the others. Before changing a crusher setting, check these in order: 1) install sub-metering on the main drives; 2) calculate specific energy weekly; 3) compare idle time against loaded running hours. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For granite at 200 t/h the working train is jaw → cone → cone / VSI → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for granite and for a softer rock. Measurements are only comparable when the sieve standard is the same.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~250 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~18 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.45 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 640 kW order-of-magnitude connected load |
The corrective actions for high energy cost per tonne are applied on top of this base circuit: meter energy against saleable tonnes, not crusher feed; match mill and classifier size to the real d97 target; add vfds to feeders and fans and interlock them with feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 20% and a screen efficiency target above 90%. A change in one stage changes the circulating load in all the others.
- Install sub-metering on the main drives
- Calculate specific energy weekly
- Compare idle time against loaded running hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 200 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–5, 5–10, 10–20, 20–40 mm |
| Crusher setting | CSS measured and logged, ~18 mm starting point |
| Power | Main-drive current at steady feed, 640 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for granite, while a verifiable mass balance determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 200 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Measurements are only comparable when the sieve standard is the same. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.